Trunkline Gas Company
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 03/27/2000, Docket: RP00-369-001, Status: Effective
Sub Sixth Revised Sheet No. 191 Sub Sixth Revised Sheet No. 191 : Effective
Superseding: Fifth Revised Sheet No. 191
GENERAL TERMS AND CONDITIONS
(Continued)
9. CAPACITY RELEASE (Continued)
Replacement Shipper is the winning bidder on a capacity
release until September 30, 2002 or is bidding the
Maximum Rate thereafter or is bidding on a second
release under a different Service Agreement;
(13) Restrictions, if any, on the PRS or Replacement
Shipper's ability to request changes in primary Points
of Receipt or primary Points of Delivery; and
(14) Whether the Shipper Notice may be rejected in part in
the event Trunkline rejects such Shipper Notice pursuant
to Section 9.7.
(B) Releasing Shipper shall post the Shipper Notice on the
Messenger system. Releasing Shipper may withdraw its
Shipper Notice at any time prior to the close of the bid
period specified in the Shipper Notice herein when
unanticipated circumstances justify and no minimum bid has
been made.
(C) When a Releasing Shipper presents a PRS that is on the
approved bidders list, such PRS shall acknowledge the Shipper
Release Notice electronically as a prerequisite to the
posting of the Shipper Notice.
(D) The terms Releasing Shipper imposes may not conflict with any
provision of the Service Agreement, Rate Schedule or General
Terms and Conditions. In the event of such conflict,
Trunkline may withdraw the Shipper Notice from posting.
9.3 Exceptions to Bidding
(A) At Shipper's option, a Shipper Notice for a release of
thirty-one (31) days or less with a designated PRS shall not
be subject to the bidding process in accordance with Section
9.4 herein (exempt capacity release). An exempt capacity
release shall not contain an evergreen provision and cannot
be reassigned to the same PRS within twenty-eight (28) Gas
Days from the termination of each release, except in the
event the PRS is the winning bidder on a capacity release
until September 30, 2002 or is bidding the Maximum Rate
thereafter or is bidding on a second release under a
different Service Agreement.