RATE SCHEDULE LFT (Continued)

LIMITED FIRM TRANSPORTATION

 

 

or FFZ which conversion shall have priority over the pending

request for service under Rate Schedule FT, EFT, QNT or FFZ which

caused such notification, assuming such Rate Schedule LFT Shipper

agrees to a service under Rate Schedule FT, EFT, QNT or FFZ that

will have a net present value that equals or exceeds the net

present value of the Rate Schedule FT, EFT, QNT or FFZ pending

request, or such notified Shipper may convert that portion of

service provided under this Rate Schedule which is equal to such

reduction to service under Rate Schedule IT or QNIT by executing a

Service Agreement for such service, or such notified Shipper may

terminate any remaining portion of service provided under this

Rate Schedule. Conversions to Rate Schedule IT or QNIT service

shall maintain the original priority date under this Rate

Schedule, for purposes of priority of service pursuant to Sections

3 and 4 of the General Terms and Conditions.

 

2.4 Flow Rate of Delivered Quantities

 

Shipper is allowed to take at any Point of Delivery during any

hour between fifty percent (50%) and one hundred fifty percent

(150%) of the uniform hourly Quantities scheduled for

Transportation to such Point of Delivery and will not incur a

daily scheduling penalty if the total Quantities delivered for the

Gas Day at such point are within the Tolerance Level specified in

Section 2.5 herein.

 

2.5 Tolerance Level

 

The Tolerance Level under this Rate Schedule LFT shall be ten

percent (10%). Daily scheduling variances in excess of the

Tolerance Level shall be subject to a daily scheduling penalty

calculated in accordance with Section 5 of the General Terms and

Conditions.