Transwestern Pipeline Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/01/1997, Docket: RP97- 18-003, Status: Effective
Fourth Revised Sheet No. 58 Fourth Revised Sheet No. 58 : Effective
Superseding: Third Revised Sheet No. 58
GENERAL TERMS AND CONDITIONS
(continued)
primary and secondary elements, shall be installed and operated as set
forth in the latest edition of ANSI/API 2530 (AGA-3), approved May 1985,
as may be superseded from time to time, for orifice meters; AGA Gas
Measurement Manual Part 2, as may be amended from time to time, for
displacement meters; and AGA Gas Measurement Manual Part 4 and AGA
Transmission Measurement Committee Report No. 7, as may be amended from
time to time, for turbine meters. The Non-Measuring party shall have
access to such measuring equipment at all reasonable hours, but the
reading, calibrating and adjusting thereof and the changing of charts
shall be done only by the Measurer.
B. The party performing measurement at an interconnect point as required by
this Tariff ("Measurer") shall furnish the interconnecting party not
performing measurement at an interconnect point ("Non-Measurer") by the
5th business day after the end of each production month a statement
reflecting the quantity of gas received or delivered during the previous
month.