Transwestern Pipeline Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 02/01/1993, Docket: RS92- 87-003, Status: Effective
3rd Revised Sheet No. 57 3rd Revised Sheet No. 57 : Effective
Superseding: 2nd Revised Sheet No. 57
GENERAL TERMS AND CONDITIONS
(continued)
F. Deviation of the natural gas from Boyle's and Charles' Laws shall be
calculated as per AGA Par Research Project NX-19 or by AGA
Transmission Measurement Committee Report No. 8, as may be amended
from time to time. The gas analysis required by Part E above shall
be used for the chemical composition of the gas as required for
calculation by NX-19 or AGA-8.
5. MEASURING STATIONS
5.1 Measuring Station:
A. Measurement facilities installed and operated hereunder shall
include standard orifice meters, turbine or standard
displacement meters, or any other method mutually agreed upon by
the interconnecting parties, and other necessary measuring
equipment by which the quantity of gas hereunder shall be
measured. The measurement facilities, including all