Texas Gas Transmission Corporation
First Revised Volume No. 2-A
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/1993, Docket: RP93-106-001, Status: Suspended
Sub Original Sheet No. 129M Sub Original Sheet No. 129M : Suspended
GENERAL TERMS AND CONDITIONS
(Continued)
29.5 Contracting for Released Capacity
(a) All Replacement Customers must contract with
Pipeline for the capacity released and assigned
to them under this Section 29 of the tariff.
(b) Before Pipeline will execute a contract with a
Replacement Customer and commence service, the
following conditions must be met:
(i) The credit criteria specified for Cus-
tomers in Pipeline's FT Rate Schedule is
met by the Replacement Customer. Such
credit criteria may be satisfied by:
A. The submission by the Replacement
Customer of the information required
by Section 12(h) of Pipeline's FT Rate
Schedule;
B. Qualifying for a Pre-approved Bidder's
List by submitting to Pipeline in
advance of bidding for capacity the
information contained in Section 12(h)
of Pipeline's FT Rate Schedule. This
"Pre-approved bidders list" will
contain the Customer's name and
approved credit limit. However, only
the preapproved bidder's name will be
posted on the EBB. Customer may be
required to update credit information
periodically in order to remain on
this "preapproved" bidders list, but
will be notified by Pipeline when this
is necessary; or
C. "Prepaying" for service as provided in
Section 12(h)(3) of Pipeline's FT Rate
Schedule.