Texas Gas Transmission Corporation

First Revised Volume No. 2-A

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/01/1993, Docket: RP93-106-001, Status: Suspended

Sub Original Sheet No. 129I Sub Original Sheet No. 129I : Suspended

 

GENERAL TERMS AND CONDITIONS

(Continued)

 

 

(c) Exceptions to Bidding Process

 

(i) If a Prearranged Replacement Customer

agrees to pay the maximum rate applicable

to the capacity offered for release and

assignment by a Releasing Customer and

agrees to all other terms and conditions

applicable to the release, then that

capacity released will not be subject to

the bidding requirements contained

herein, but Pipeline will post infor-

mation describing such a release of

capacity to its EBB at least forty-eight

(48) hours after transportation commences

for the Replacement Customer.

 

(ii) If a Releasing Customer has obtained a

Prearranged Replacement Customer, in

relation to a release of capacity for

less than one calendar month, or for a

volume which is less than 10,000 MMBtu

per day, then that capacity released will

not be subject to the bidding

requirements contained herein, but Pipe-

line will post information describing

such a release of capacity to its EBB at

least forty-eight (48) hours after trans-

portation commences for the Replacement

Customer. However, no "roll-overs or

extensions" of such transactions will be

allowed without complying with the

bidding process, herein, unless such

Prearranged Replacement Customer agrees

to pay the maximum rate for that capacity

and meet all other terms and conditions

set by the Releasing Customer.

 

(iii) For releases described in (i) and (ii)

above, Releasing Customers must notify

Pipeline of the terms of the release