Texas Gas Transmission Corporation
First Revised Volume No. 2-A
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/1991, Docket: RP90-192-005, Status: Effective
First Revised Sheet No. 49 First Revised Sheet No. 49 : Effective
Superseding: Substitute Original Sheet No. 49
RATE SCHEDULE
IT-SL, IT-1, IT-2, IT-3 and IT-4
Interruptible Transportation Service
(Continued)
Based on the above listed criteria, a project
shall be economically beneficial when the
projected first year incremental revenues equal
or exceed the projected first year incremental
cost of service. When the project is deter-
mined to be economically beneficial, Trans-
porter will pay for the cost of the contem-
plated facilities. When the delivery point
facilities do not qualify under the economic
test of this section, the facilities shall be
installed at Customer's expense.
When Transporter has previously paid for all or
a portion of delivery point facilities under
this facilities reimbursement policy, Customer
shall, nevertheless, promptly pay Transporter
for Transporter's net book value of such
facilities when either of the following events
occurs: (1) when Transporter's ability to
fully recover such costs is denied in any
Section 4 or Section 5 rate proceeding, or (2)
when Customer ceases operations at the delivery
point where the facilities were installed.
(b) Transporter shall not construct or modify any
facilities hereunder which will result in an
increase or decrease in Transporter's mainline
capacity, or which may compromise the opera-
tional integrity of Transporter's pipeline
system. For those facilities which Transporter
agrees to construct, Transporter will construct
those facilities (1) pursuant to and subject to
the authorization granted in Subpart F of Part
157 of the Regulations of the Federal Energy
Regulatory Commission or (2) where the prior
authorization of the Federal Energy Regulatory
Commission is not required to construct such
facilities.