Sea Robin Pipeline Company
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/04/1997, Docket: RP97-411-003, Status: Effective
First Substitute Original Sheet No. 130L First Substitute Original Sheet No. 130L : Superseded
Superseding: Original Sheet No. 130l
Rate Schedule FTS-2
Firm Transportation Service
(Continued)
(d) SHIPPER shall have the right for any reason, at any
time and from time to time, to permanently change, in
whole or in part, the MDQs under its FTS-2 Agreement, for
any Delivery Period(s) set forth on Exhibit A thereto, on
six (6) months prior written notice to TRANSPORTER;
provided, however, any increases in MDQ under the FTS-2
Agreement shall be subject to availability of firm
capacity on the system as determined by TRANSPORTER
hereunder. If firm capacity is not available, SHIPPER
may request that such MDQ increase be placed in
TRANSPORTER'S firm service queue pursuant to Section 4(f)
and 4(g) below and TRANSPORTER will place it in the firm
service queue as a pending request as of the date of
SHIPPER'S update.
(e) TRANSPORTER shall date and time stamp all
transportation requests for service under this Rate
Schedule FTS-2 as they are received. A request for
service shall be valid as of the date of receipt ("Valid
Date") provided that all the necessary information
described herein has been provided. A request shall not
be valid if TRANSPORTER informs SHIPPER that the service
requested does not conform to the terms of this Rate
Schedule FTS-2, that the data provided is incomplete or
not adequately substantiated.
TRANSPORTER may waive any requirement of this Section if,
in its reasonable judgment and on a non-discriminatory
basis, TRANSPORTER deems the information unnecessary or
irrelevant to TRANSPORTER'S request. TRANSPORTER may
request