Pacific Gas Transmission Company

Second Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/01/1990, Docket: RP90-109-000, Status: Effective

Original Sheet No. 105 Original Sheet No. 105 : Superseded

 

GENERAL TERMS AND CONDITIONS

(Continued)

 

5. MEASURING EQUIPMENT

 

5.3 (Continued)

 

(c) If neither of the methods provided in (a) and (b) above

can be used, by estimating the quantity delivered, by

reference to deliveries under similar conditions during a

period when the equipment was registering accurately.

 

No correction shall be made in the recorded quantities of gas

delivered hereunder for measuring equipment inaccuracies of

two percent (2%) or less, and in no event shall inaccuracies

less than 25 Mcf be considered for adjustment.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Continued)