Pacific Gas Transmission Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/1990, Docket: RP90-109-000, Status: Effective
Original Sheet No. 105 Original Sheet No. 105 : Superseded
GENERAL TERMS AND CONDITIONS
(Continued)
5. MEASURING EQUIPMENT
5.3 (Continued)
(c) If neither of the methods provided in (a) and (b) above
can be used, by estimating the quantity delivered, by
reference to deliveries under similar conditions during a
period when the equipment was registering accurately.
No correction shall be made in the recorded quantities of gas
delivered hereunder for measuring equipment inaccuracies of
two percent (2%) or less, and in no event shall inaccuracies
less than 25 Mcf be considered for adjustment.
(Continued)