FORM OF SERVICE AGREEMENT

APPLICABLE TO AUTHORIZED IMBALANCE SERVICE

UNDER RATE SCHEDULE AIS-1

 

THIS AGREEMENT is made and entered into this _____ day of

________, 19__, by and between

 

PG&E GAS TRANSMISSION, NORTHWEST CORPORATION, a California corporation

(hereinafter referred to as "PG&E GT-NW"),and

__________________________, a corporation existing under the laws of the

State or Province of _______________ (hereinafter referred to as

"Shipper"), on behalf of ___________________ (hereinafter referred to as

____________________________)

 

WHEREAS, PG&E GT-NW owns and operates a natural gas pipeline transmission

system which extends from a point of interconnection with the pipeline

facilities of Alberta Natural Gas Company Ltd. (ANG) at the International

Boundary near Kingsgate, British Columbia, through the states of Idaho,

Washington and Oregon to a point of interconnection with Pacific Gas and

Electric Company at the Oregon-California border near Malin, Oregon; and

 

WHEREAS, Shipper desires PG&E GT-NW, on an interruptible basis, to obtain

short-term advances of certain quantities of natural gas; and

 

WHEREAS, PG&E GT-NW is willing to advance, on a short-term basis, certain

quantities of natural gas for Shipper, on an interruptible basis,

 

NOW, THEREFORE, the parties agree as follows:

 

I

Governmental Authority

 

1.1 This Authorized Imbalance Service Agreement ("Agreement") is made

pursuant to the regulations of the Federal Energy Regulatory

Commission (FERC) contained in 18 CFR Part 284, as amended from time

to time.

 

1.2 This Agreement is subject to all valid legislation with respect to

the subject matters hereof, either state or federal, and to all valid

present and future decisions, orders, rules, regulations and

ordinances of all duly constituted governmental authorities having

jurisdiction.

 

1.3 Shipper shall reimburse PG&E GT-NW for any and all filing fees

incurred by PG&E GT-NW in seeking governmental authorization for the

initiation, extension, or termination of service under this

Agreement and Rate Schedule AIS-1. Shipper shall reimburse PG&E GT-NW

for such fees at PG&E GT-NW's designated office within ten (10) days

of receipt of notice from PG&E GT-NW that such fees are due and

payable. (Continued)