Pacific Gas Transmission Company
First Revised Volume No. 1-A
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/01/1999, Docket: RP99-248-000, Status: Effective
Fourth Revised Sheet No. 16B Fourth Revised Sheet No. 16B : Effective
Superseding: Third Revised Sheet No. 16B
RATE SCHEDULE FTS-1
FIRM TRANSPORTATION SERVICE (Continued)
3.12 Reservation Charge Credit - Other than Malin Primary Delivery Point
If PG&E GT-NW fails to deliver Forward-haul service on a Primary
Path to a primary delivery point on its system other than Malin,
Oregon, ninety-five percent (95%) or more of the aggregate
Confirmed Daily Nominations (as hereinafter defined) of all
Shippers at such primary delivery point other than Malin receiving
service under this rate schedule (hereinafter referred to as the
"Non-Deficiency Amount") for more than twenty-five (25) days in
any given Contract Year, then for each day during that Contract
Year in excess of twenty-five (25) days that PG&E GT-NW so fails
to deliver the Non-Deficiency Amount (a "Credit Day") Shipper, as
its sole remedy, shall be entitled to a Reservation Charge Credit
calculated in the manner hereinafter set forth.
For the purpose of this Paragraph 3.12, Confirmed Daily
Nomination shall mean for any day, the lesser of (1) Shipper's
Maximum Daily Quantity or (2) the quantity of gas that the
connecting downstream pipeline(s), local distribution company
pipeline(s), or end-user(s) is/are capable of accepting for
Shipper's account at Shipper's point(s) of primary delivery on
PG&E GT-NW or (3) the quantity of gas that the connecting pipeline
upstream of PG&E GT-NW is capable of delivering to PG&E GT-NW for
Shipper's account to PG&E GT-NW at Shipper's primary point of
receipt(s) on PG&E GT-NW less Shipper's requirement to provide
compressor fuel and line losses under the Statement of Effective
Rates and Charges of PG&E GT-NW's FERC Gas Tariff, First Revised
Volume No. 1-A or (4) Shipper's nomination to PG&E GT-NW.
The Reservation Charge Credit for each Credit Day for a
particular Shipper shall be computed as follows:
Reservation Charge A B - C
Credit for Each ____ x _____
Credit Day = (30.4 ) ( B )
where A = Shipper's Monthly Reservation Charge
B = Shipper's confirmed daily nomination for the
Credit Day
C = Actual quantity of gas delivered by PG&E GT-NW to a
Shipper's primary delivery point(s) (other than
Malin) for Shipper's account for the Credit Day
Except as provided for in Paragraph 3.10 of this rate schedule
this Reservation Charge Credit is Shipper's sole remedy for
nondelivery of gas by PG&E GT-NW.
(Continued)