Pacific Gas Transmission Company

First Revised Volume No. 1-A

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 01/01/2001, Docket: RP01-153-000, Status: Suspended

Twenty-Fifth Revised Sheet No. 5 Twenty-Fifth Revised Sheet No. 5 : Suspended

Superseding: Substitute Twenty-Fourth Revised Sheet N

STATEMENT OF EFFECTIVE RATES AND CHARGES

FOR TRANSPORTATION OF NATURAL GAS

 

Notes:

 

(a) The mileage component shall be applied per pipeline mile to gas

transported by PG&E GT-NW for delivery to shipper based on the

primary receipt and delivery points in Shipper's contract. Consult

PG&E GT-NW's system map on Sheet 3 for receipt and delivery point and

milepost designations.

 

(b) The non-mileage component is applied per Shipper's MDQ at Primary

Point(s) of Delivery on Mainline Facilities.

 

(c) The delivery rates are applied per pipeline mile to gas transported by

PG&E GT-NW for delivery to shipper based on distance of gas

transported. Consult PG&E GT-NW's system map on Sheet No. 3 for

receipt and delivery point and milepost designations.

 

(d) Fuel Use: Shipper shall furnish gas used for compressor station fuel,

line loss, and other utility purposes, plus other unaccounted-for gas

used in the operation of PG&E GT-NW's combined pipeline system in an

amount equal to the sum of the current fuel and line loss

percentage and the fuel and line loss percentage surcharge in

accordance with Paragraph 37 of this tariff, multiplied by the

distance in pipeline miles transported from the receipt point to the

delivery point multiplied by the transportation quantities of gas

received from Shipper under these rate schedules. The current fuel and

line loss percentage shall be adjusted each month between the maximum

rate of 0.0041% per Dth per pipeline mile and the minimum rate of

0.0000% per Dth per mile. The fuel and line loss percentage surcharge

is 0.0012% per Dth per pipeline mile. No fuel use charges will be

assessed for backhaul service.

 

(e) The MRRS Surcharge applies to Subject Shippers pursuant to Paragraph

3.1(c) of Rate Schedule FTS-1 and Article IV, Section 1(c) of the

Stipulation and Agreement in Docket No. RP94-149-000.

 

(f) Applicable to firm service on PG&E GT-NW's Medford Extension.

 

 

 

 

 

 

 

 

(Continued)