8. NOMINATIONS, SCHEDULING, AND CURTAILMENT (Continued)
(b) In the event of a curtailment pursuant to Section
8.3(a) above, interruptible and authorized overrun services shall
be curtailed first. Interruptible and authorized overrun services
shall be curtailed from lowest to highest rate. Interruptible and
authorized overrun Customers may elect to waive discounts during
curtailments; any such election shall be reflected in any discount
agreement between MRT and the Customer. Interruptible and
authorized overrun services at maximum rate shall be curtailed
after all discounted interruptible and authorized overrun services
have been curtailed. In the event interruptible and authorized
overrun transportation services at the same rate must be
curtailed, quantities without flowing priority (as defined in
Section 8.2(c)(v) shall be curtailed before quantities with
flowing priority. In the event that interruptible and authorized
overrun service at the same rate with the same flowing priority
(if applicable) must be curtailed, service shall be curtailed pro
rata based on confirmed nominations. Following the curtailment of
all interruptible and authorized overrun transportation services,
firm transportation service shall be curtailed pro rata based on
each Customer's MDQ in each zone. Following the curtailment of
all interruptible and authorized overrun storage withdrawals, firm
storage withdrawals shall be curtailed pro rata based on each
Customer's current maximum daily deliverability. Following the
curtailment of all interruptible and authorized overrun storage
injections, firm storage injections will be curtailed pro rata
based on contracted storage capacity.
(c) All volumes received and/or taken in violation of
MRT's curtailment or interruption orders shall constitute
unauthorized receipts or deliveries of gas for which a charge of
$20.00 per MMBtu shall be assessed in addition to any other
applicable rate, charge or penalty. Such charge shall be
applicable to all such unauthorized receipts and deliveries
following notification of curtailment or interruption, in
violation of curtailment or interruption orders issued by MRT,
which orders may be given by telephone, confirmed by facsimile
transmission or any other reasonable means.