Texas Eastern Transmission Corporation

Sixth Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 06/01/1993, Docket: RS92- 11-009, Status: Effective

Original Sheet No. 916 Original Sheet No. 916 : Effective

 

FORM OF SERVICE AGREEMENT

FOR RATE SCHEDULE SS

(Continued)

 

In the event there is gas in storage for Customer's account on April 30 of

the year of termination of this Service Agreement, this Service Agreement shall

continue in force and effect for the sole purpose of withdrawal and delivery of

said gas to Customer for an additional one-hundred and twenty (120) days.

 

ARTICLE III

 

RATE SCHEDULE

 

This Service Agreement in all respects shall be and remain subject to the

applicable provisions of Rate Schedule SS and of the General Terms and Conditions

of Pipeline's FERC Gas Tariff on file with the Federal Energy Regulatory

Commission, all of which are by this reference made a part hereof.

 

Customer shall pay Pipeline, for all services rendered hereunder and for the

availability of such service in the period stated, the applicable prices

established under Pipeline's Rate Schedule SS as filed with the Federal Energy

Regulatory Commission and as same may hereafter be legally amended or superseded.

 

Customer agrees that Pipeline shall have the unilateral right to file with

the appropriate regulatory authority and make changes effective in (a) the rates

and charges applicable to service pursuant to Pipeline's Rate Schedule SS, (b)

Pipeline's Rate Schedule SS, pursuant to which service hereunder is rendered or

(c) any provision of the General Terms and Conditions applicable to Rate Schedule

SS. Notwithstanding the foregoing, Customer does not agree that Pipeline shall

have the unilateral right without the consent of Customer subsequent to the

execution of this Agreement and Pipeline shall not have the right during the

effectiveness of the service agreement to make any filings pursuant to Section 4

of the Natural Gas Act to change the MSQ and MDQ specified in Article I, to

change the term of the service agreement as specified in Article II, to change

Point(s) of Receipt specified in Article IV, to change the Point(s) of Delivery

specified in Article IV, or to change the firm character of the service

hereunder. Pipeline agrees that Customer may protest or contest the afore-

mentioned filings, or may seek authorization from duly constituted regulatory

authorities for such adjustment of Pipeline's existing FERC Gas Tariff as may be

found necessary to assure that the provisions in (a), (b), or (c) above are just

and reasonable.

 

ARTICLE IV

 

POINT(S) OF RECEIPT AND POINT(S) OF DELIVERY

 

The natural gas received by Pipeline for Customer's account for storage

injection pursuant to this Service Agreement shall be those quantities scheduled

for delivery pursuant to service agreements between Pipeline and Customer under

Rate Schedules CDS, FT-1, IT-1 or PTI which specify as a Point of Delivery the

"SS Storage Point". For purposes of billing of Usage Charges under Rate

Schedules CDS, FT-1, IT-1 or PTI