Texas Eastern Transmission Corporation
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/1993, Docket: RS92- 11-009, Status: Effective
Original Sheet No. 618 Original Sheet No. 618 : Effective
GENERAL TERMS AND CONDITIONS
(Continued)
applicable zone and rate schedule by the estimated demand and
commodity units to be billed weighted on the basis of the
Base Electric Power Cost Units for each applicable zone and
rate schedule under all EPC Rate Schedules for the twelve
month period beginning February 1. The EPC Surcharges for
each applicable zone and rate schedule shall be rounded to
the nearest 1/100 of a cent for commodity surcharges and
1/1000 of a dollar for demand surcharges.
(5) Base Electric Power Cost Unit
The Base Electric Power Cost Unit for each applicable zone
and rate schedule which are the unit Electric Power Costs
included in the Base Tariff Rates under Pipeline's EPC Rate
Schedules shall be reflected on Sheet Nos. 130 through 133 of
this FERC Gas Tariff.
(6) EPC Adjustment
The Current Unit EPC Change for each applicable zone and rate
schedule computed in accordance with Section 15.1(B)(2) and
the EPC Surcharge computed in accordance with Section
15.1(B)(4) above shall be added to the applicable demand and
commodity components of Pipeline's EPC Rate Schedules and the
last previous units computed under the same sections, which
are contained in such rates, if any, shall be removed. Rate
adjustments hereunder shall be applied to Pipeline's rates in
such a manner that historical rate design concepts shall be
maintained. In the event a change in rates under the
provisions of this Section 15.1 is prevented by law from
going into effect on a date specified herein, it shall be
made effective as soon thereafter as permitted by law.
(C) Procedure for Filing:
Pipeline shall file and place into effect, subject to suspension
for not more than one day, changes in its jurisdictional rates to
reflect any increase or decrease in the cost to Pipeline for the
use of electric power. Filings hereunder shall be made effective
on February 1 and August 1. Not less than thirty (30) days prior
to the proposed effective date of a rate change pursuant to this
Section 15.1, Pipeline shall file with the Commission and shall
mail to each of its jurisdictional Customers, and interested state
commissions revised tariff sheets reflecting the proposed rate
change together with a statement showing the computation of the
rate change. The filing effective February 1 each year shall
include revised EPC Surcharges computed pursuant to Section
15.1(B)(4) above and revised Current Unit EPC Changes computed in
accordance with Section 15.1(B)(2); however, the filing effective