Texas Eastern Transmission Corporation
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/1993, Docket: RS92- 11-009, Status: Effective
Original Sheet No. 617 Original Sheet No. 617 : Effective
GENERAL TERMS AND CONDITIONS
(Continued)
(2) Current Unit EPC Change
The Current Unit EPC Change based on the Base Electric Power
Cost Units under Section 15.1(B)(5) hereof shall be computed
as the difference obtained by subtracting the Base Electric
Power Cost Unit for each applicable zone and rate schedule
from the quotient obtained by dividing the estimated annual
electric power costs as defined in Section 15.1(B)(1) above
for the applicable zones and rate schedules for the 12 months
beginning with the effective date of the adjustment,
allocated in accordance with the then currently effective
method in use for allocating Transmission Costs on Pipeline's
system, by the estimated demand and commodity units to be
billed under the applicable zones and rate schedules under
Section 15.1(B)(5) for the same period. The Current Unit EPC
Change for applicable zones and rate schedules will be
rounded to the nearest 1/100 of a cent for commodity rate
adjustments and 1/1000 of a dollar for demand adjustments.
The Current Unit EPC change as determined on the Base
Electric Power Cost Units under Section 15.1(B)(5) hereof
shall be based on such change as determined with respect to
the Base Electric Power Cost Units under Section 15.1(B)(5)
in such a manner that historical rate design concepts shall
be maintained.
(3) Deferred EPC Account
A Deferred EPC Account shall be maintained reflecting the
under collection or over collection of Electric Power Costs
for each monthly billing period. The Deferred EPC Account
shall be credited or debited as follows: Each month all
Electric Power Costs as defined in Section 15.1(B)(1) above
incurred by Pipeline shall be debited to this account and all
Electric Power Costs recovered by Pipeline shall be credited
to this account. Electric Power Cost recoveries will be
determined by multiplying the sum of the applicable Base
Electric Power Cost Unit plus the corresponding effective EPC
Adjustment for each zone and rate schedule by the respective
monthly demand and commodity units to be billed. Beginning
on June 1, 1993 or the effective date of this Section
15.1(B)(3), the Deferred EPC Account shall be maintained in
twelve-month accumulation periods, November-October, provided
that the first accumulation period shall include any balance
carried forward from prior periods.
(4) Electric Power Cost (EPC) Surcharge Adjustments
The Electric Power Cost Surcharge Adjustments shall be
computed for each applicable zone and rate schedule by
dividing the Deferred EPC Account Balance for such