GENERAL TERMS AND CONDITIONS
(Continued)
Firm Capacity may be designated as MDDO or MDRO to the
extent (1) such Customer's MDDO or MDRO, as applicable, is
less than its MDQ, or (2) such Customer requests that an
equivalent quantity of existing MDDO or MDRO, as applicable,
under Customer's executed service agreements be designated
as Section 14.9 Firm Capacity. Any capacity awarded under
this Section 14.10 for a new firm service shall be
designated as MDDO, or MDRO, as applicable, in the
applicable exhibit of each requesting Customer's executed
service agreement(s) under such new firm service.
(B) Unutilized Section 14.9 Firm Capacity may be recalled to
fulfill requests under Section 14.10(A). In the event it is
necessary for Pipeline to recall Section 14.9 Firm Capacity
to satisfy a request under Section 14.10, Section 14.9 Firm
Capacity may be retained by a Customer based on the usage of
the point for up to a twelve-month period prior to the date
of a valid request. Quantities delivered or received by
such Customer during such evaluation period will be utilized
to determine the Customer's Firm Peak Day Quantity. The
Firm Peak Day Quantity, for purposes of this Section 14.10,
shall be the greatest daily quantity utilized for such
period under Rate Schedules CDS, FT-1, SCT, and/or SS-1 at
each Section 14.9 Firm Capacity point. The quantity of
Section 14.9 Firm Capacity that may be retained at each
point by a Customer shall be determined as follows.
(1) If the point does not have an MDDO or an MDRO, as
applicable, on the exhibit(s) to the Customer's
executed service agreements under Rate Schedules CDS,
FT-1, SCT, and/or SS-1, the quantity retained will be
limited to the greater of:
(a) the Customer's existing Section 14.9 Firm Capacity
less the quantity required to meet a valid request
at the point, if one hundred ten percent (110%) of
the Firm Peak Day Quantity is less than the
Customer's existing Section 14.9 Firm Capacity; or
(b) the lesser of (i) one-hundred ten percent (110%)
of the Firm Peak Day Quantity, or (ii) the
Customer's existing Section 14.9 Firm Capacity.
(2) If the point does have an MDDO or an MDRO, as
applicable, on the exhibit(s) to the Customer's
executed service agreements under Rate Schedules CDS,
FT-1, SCT, and/or SS-1, the quantity retained will be
limited to the greater of: