Texas Eastern Transmission Corporation
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/1993, Docket: RS92- 11-013, Status: Effective
Sub Original Sheet No. 604 Sub Original Sheet No. 604 : Effective
Superseding: Original Sheet No. 604
GENERAL TERMS AND CONDITIONS
(Continued)
(iii) the requirement that Pipeline shall not deliver for the
account of Customer in the aggregate at all Point(s) of
Delivery hereunder a quantity of gas in excess of the
Customer's rights in any portion of Pipeline's system which
are defined in the Access Area by the Operational Segment
Capacity Entitlements and in the Market Area by the
Customer's Transportation Path(s).
(iv) The requirement that quantities nominated at Points of
Delivery located on a third party pipeline meet all of the
terms and conditions prescribed in third party pipeline's
effective FERC Gas Tariff and the applicable service
agreement with the third party pipeline.
14.9 Open-season
(A) Pipeline shall endeavor to accommodate a request from any
Customer under Rate Schedules CDS, FT-1, SCT, and/or SS-1
for any specific point on Pipeline's system as a firm Point
of Receipt and/or as a firm Point of Delivery promptly upon
receipt of the request. Pipeline's consent to any request
for any specific point as a firm Point of Receipt or as a
firm Point of Delivery shall not be unreasonably withheld.
Pipeline shall not accept any proposed Point of Receipt, any
quantity at any Point of Receipt, any change in quantities
among firm Points of Receipt, any Point of Delivery, any
quantity at any Point of Delivery, or any change in
quantities among firm Points of Delivery if in doing so, in
Pipeline's reasonable judgment, such acceptance would impair
Pipeline's ability to satisfy Pipeline's existing firm
obligations to receive gas under other firm agreements
and/or to satisfy Pipeline's existing firm obligations to
deliver gas under other firm agreements.
(B) For any existing uncommitted firm capacity at Point(s) of
Delivery, Pipeline shall hold an open-season for thirty (30)
days beginning on July 1, 1993 to allow requests for such
Points posted on the LINKþ System as of July 1, 1993. For
uncommitted firm capacity at any Point(s) of Delivery or
Point(s) of Receipt constructed on and after July 1, 1993
available pursuant to Section 14.5(B) or 14.6(B),
respectively, Pipeline shall hold an open-season for fifteen
(15) days beginning on the first business day of each month
to allow requests for Points of Receipt or Points of
Delivery posted on the LINKþ System during the previous
calendar month as "Newly Constructed". Such posting shall
include the in-service date for the facilities.
(C) Pipeline shall allocate capacity available at such Point(s)
of Receipt or Point(s) of Delivery on a pro rata basis up to
each Customer's firm Transportation Path entitlement at such
Point(s) of Receipt or Point(s) of Delivery, as applicable,
based upon the aggregate Transportation Path entitlement at