Texas Eastern Transmission Corporation
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/1994, Docket: RP94-314-000, Status: Effective
Original Sheet No. 354 Original Sheet No. 354 : Effective
RATE SCHEDULE FTS-7
(Continued)
Such Customers at any time may request, in a form suitable to Pipeline, to
firm up, as firm service under this Rate Schedule, any portion of its MDQ
under the applicable Rate Schedule IT-1 Service Agreement. Upon receipt of
such a request, Pipeline shall inquire of all Customers under this Rate
Schedule if they also desire at such time to firm up any portion of their
respective Rate Schedule IT-1 MDQ. If Pipeline receives sufficient
requests for firmed up MDQ which, in Pipeline's sole opinion, makes it
economically feasible to expand Pipeline's system, Pipeline shall make the
necessary expansion of its system as soon as practicable after all
necessary regulatory and governmental authorizations on terms and
conditions acceptable to Pipeline are granted. Upon completion of the
system expansion, Pipeline shall notify each Customer which requested a
firmed up MDQ of its new MDQ under this Rate Schedule and the effective
date thereof. The annual costs associated with all facilities which must
be added to Pipeline's system to enable the establishment of and firm up of
the MDQ's of Customers hereunder shall be borne by those Customers which
have MDQ's hereunder by means of the Reservation Charge.
11. GENERAL TERMS AND CONDITIONS
All of the General Terms and Conditions of Pipeline's FERC Gas Tariff
of which this Rate Schedule is a part are applicable to this Rate Schedule
and are made a part hereof to the extent that such terms and conditions are
not contradicted by any provision herein.