RATE SCHEDULE FTS-7

(Continued)

 

(E) occurs either (1) within ten (10) days following a force majeure

event as contemplated by Section 17.1 of the General Terms and

Conditions, or (2) prior to the date Pipeline has or should have,

in the exercise of due diligence, overcome the force majeure

event, whichever occurs first.

 

provided, however, 3.5(C) and 3.5(D) are also subject to the notice and due

diligence requirements of Section 17.3 of the General Terms and Conditions.

 

4. MINIMUM COMMODITY BILL

 

None.

 

5. SCHEDULING OF RECEIPTS AND DELIVERIES

 

If Customer desires transportation of natural gas on any day under this Rate

Schedule, Customer shall give notice to Pipeline in accordance with Section 4 of

Pipeline's General Terms and Conditions.

 

6. DETERMINATION OF DELIVERIES

 

If Pipeline delivers natural gas to Customer under this Rate Schedule at the

same Point(s) of Delivery on the same day that Pipeline delivers natural gas to

Customer under any other rate schedule, then the quantity of natural gas

delivered under this Rate Schedule shall be determined in accordance with the

provisions of Section 18 of Pipeline's General Terms and Conditions of this FERC

Gas Tariff.

 

7. IMPAIRMENT OF RECEIPTS AND DELIVERIES

 

Where Pipeline, on any day is unable to receive and/or deliver the total

requests of all of its Customers due to force majeure on Pipeline's system, then

Pipeline shall limit receipts and/or deliveries of gas hereunder in accordance

with Section 4 of Pipeline's General Terms and Conditions.

 

8. RATE SCHEDULE SS-2 CONVERSIONS

 

Those Rate Schedule SS-2 service agreements previously entered into by

Customers with Pipeline for firm storage service shall be deemed Rate Schedule

FTS-7 Service Agreements to the extent of such firm service. Interruptible

service previously provided under Customer's SS-2 Agreement shall be offered

pursuant to a Rate Schedule IT-1 Service Agreement. As of the effective date of

this Section 8, the rights and obligations of the parties to Rate Schedule SS-2

to the extent of such firm service shall be determined pursuant to this Rate