(E) occurs either (1) within ten (10) days following a force majeure

event as contemplated by Section 17.1 of the General Terms and

Conditions, or (2) prior to the date Pipeline has or should have,

in the exercise of due diligence, overcome the force majeure

event, whichever occurs first.

 

provided, however, 3.5(C) and 3.5(D) are also subject to the notice and due

diligence requirements of Section 17.3 of the General Terms and Conditions.

 

4. MINIMUM COMMODITY BILL

 

None.

 

5. SCHEDULING OF RECEIPTS AND DELIVERIES

 

If Customer desires the transportation of gas on any day under this Rate

Schedule, Customer shall give notice to Pipeline in accordance with Section 4 of

Pipeline's General Terms and Conditions.

 

6. DETERMINATION OF DELIVERIES

 

If Pipeline delivers natural gas to Customer under this Rate Schedule at the

same Point(s) of Delivery on the same day that Pipeline delivers natural gas to

Customer under any other rate schedule, then the quantity of natural gas

delivered under this Rate Schedule shall be determined in accordance with the

provisions of Section 18 of Pipeline's General Terms and Conditions of this FERC

Gas Tariff.

 

7. IMPAIRMENT OF RECEIPTS AND DELIVERIES

 

Where Pipeline, on any day is unable to receive and/or deliver the total

requests of all of its Customers due to force majeure on Pipeline's system, then

Pipeline shall limit receipts and/or deliveries of gas hereunder in accordance

with Section 4 of Pipeline's General Terms and Conditions.

 

8. IMBALANCES

 

Except to the extent Point of Receipt and Point of Delivery imbalances are

reconciled and resolved pursuant to Rate Schedule(s) TABS-1 and/or MBA, as

applicable, imbalances shall be reconciled and resolved pursuant to Section 8 of

Pipeline's General Terms and Conditions.

 

9. GENERAL TERMS AND CONDITIONS

 

All of the General Terms and Conditions of Pipeline's FERC Gas Tariff of

which this Rate Schedule is a part are applicable to this Rate Schedule and are

made a part hereof to the extent that such terms and conditions are not