RATE SCHEDULE ISS-1

(Continued)

 

(B) Injection Charge:

 

The Injection Charge Rate, as determined pursuant to Section 3.1

herein, multiplied by the quantity of gas injected pursuant to

Rate Schedule ISS-1 for the month.

 

(C) Withdrawal Charge:

 

The applicable Withdrawal Charge Rate, as determined pursuant to

Section 3.1 herein, multiplied by the quantity of gas withdrawn

from storage pursuant to Rate Schedule ISS-1 for the month.

 

4. MINIMUM COMMODITY BILL

 

None.

 

5. INJECTION PROVISIONS

 

5.1 General Procedure If Customer desires Pipeline to store gas for

Customer's account under this Rate Schedule, it shall give notice to Pipeline

specifying the quantity of gas, not in excess of the MDIQ, which Customer desires

to be injected into storage under this Rate Schedule on such day. Subject to

Section 7 of Rate Schedule ISS-1, Pipeline shall thereupon inject the quantity of

gas so nominated subject to the limitations set forth herein.

 

5.2 Pipeline shall permit transfers of title of gas in Storage Inventory,

provided both Customers have executed a service agreement under Rate Schedules

SS-1, FSS-1 and/or ISS-1 and that such transfer does not permit either Customer

to exceed its MSQ specified in such service agreement. Such transferred

quantities shall not be included in any Customer's Storage Inventory for purposes

of determining Customer's daily withdrawal rights until twenty-four (24) hours

following the date of transfer.

 

5.3 In addition to accepting gas for storage injection at the ISS-1 Storage

Point, Pipeline will accept gas tendered at points of interconnection between

Pipeline and third party facilities at Oakford and Leidy Storage Fields provided

that such receipt does not result in Customer tendering aggregate quantities for

storage in excess of the Customer MDIQ.

 

5.4 Notice Required The notice given by Customer to Pipeline for

injections on any day shall be in accordance with Section 4 of Pipeline's General

Terms and Conditions of this FERC Gas Tariff.