Texas Eastern Transmission Corporation
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/1993, Docket: RS92- 11-009, Status: Effective
Original Sheet No. 308 Original Sheet No. 308 : Effective
RATE SCHEDULE ISS-1
INTERRUPTIBLE STORAGE SERVICE
1. AVAILABILITY
This open-access Rate Schedule is available to any party (hereinafter
called Customer) which has requested interruptible storage service pursuant
to Section 3 of Texas Eastern Transmission Corporation's (hereinafter
called Pipeline) General Terms and Conditions and after review and
acceptance of such request by Pipeline, has entered into a service
agreement with Pipeline for service under Rate Schedule ISS-1 and has
entered into a service agreement under Pipeline's Transportation Rate
Schedules CDS, SCT, FT-1 and/or IT-1 (hereinafter referred to as "Rate
Schedule ISS-1 Transportation Rate Schedules") which provide for the
receipt and delivery of gas attributable to Rate Schedule ISS-1 service.
Such service agreements shall be in the form contained in Pipeline's FERC
Gas Tariff of which this Rate Schedule ISS-1 is a part.
2. APPLICABILITY AND CHARACTER OF SERVICE
2.1 This Rate Schedule shall apply to all interruptible storage
service rendered hereunder pursuant to an executed service agreement
providing for a Maximum Storage Quantity (MSQ), Maximum Daily Injection
Quantity (MDIQ), and a Maximum Daily Withdrawal Quantity (MDWQ).
Withdrawal service under this Rate Schedule constitutes one of the "no-
notice" service options as that term is used in Order No. 636 available
from Pipeline.
2.2 Interruptible Storage Service shall be available only to the
extent that the injection, storage and withdrawal capacity designated for
Rate Schedules SS-1 and FSS-1 firm storage service is not required for such
firm storage service and to the extent such injection, storage and
withdrawal capacity is not required to satisfy Pipeline's other firm
obligations under its firm rate schedules. Pipeline shall be entitled to
refuse to perform service under Rate Schedule ISS-1 when Customer cannot
demonstrate to Pipeline's satisfaction that Customer will have the ability
to transport away from storage ISS-1 gas quantities Customer is required to
withdraw when such storage capacity is needed to satisfy Pipeline's firm
obligations. To the extent storage capacity which is being utilized by a
Customer hereunder is needed by Pipeline in order to satisfy Pipeline's
firm obligations under Rate Schedules SS-1 and FSS-1 or to accommodate
Pipeline's firm obligations under its firm rate schedules, Pipeline shall
require Customer to withdraw all, or any portion thereof, ISS-1 gas
quantities held in storage by Pipeline for Customer's account within three
(3) days of Pipeline's notice. If Customer is able to schedule the
transportation of such gas under Customer's highest priority transportation
service agreement during such three (3) day period and fails to withdraw
such ISS-1 storage gas then Pipeline shall take title to such ISS-1 Storage
Inventory Customer was instructed to withdraw, free and clear of any
adverse claims. Pipeline's notice to Customer shall be verbal and may be
followed by a written confirmation.