RATE SCHEDULE SS-1

(Continued)

 

(D) Withdrawal Charge:

 

The Withdrawal Charge Rate, as determined pursuant to Section 3.1

herein, multiplied by the quantity of gas scheduled and withdrawn

for the month, other than Excess Withdrawal Gas, pursuant to the

executed service agreement;

 

(E) Excess Injection Charge:

 

The Excess Injection Charge Rate, as determined by Section 3.1

herein, multiplied by the quantities of Excess Injection Gas

received for the month pursuant to the executed service agreement;

 

(F) Excess Withdrawal Charge:

 

The Excess Withdrawal Charge Rate, as determined by Section 3.1

herein, multiplied by the quantities of Excess Withdrawal Gas

delivered for the month pursuant to the executed service

agreement;

 

3.3 In addition to all other charges hereunder, the Customers specified on

Sheet No. 45 shall pay Pipeline the applicable Incremental Facility Charge, as

set forth on Sheet No. 45, per month per Dth of additional MSQ, MDWQ and/or MDIQ,

as applicable, for which each Customer contracted under Pipeline's various

incremental facility expansions. The additional Dth applicable for each Customer

under each applicable incremental facility expansion are set forth on Sheet No.

45.

 

3.4 Except as provided in Section 3.5 of this Rate Schedule, in the event

Pipeline fails to deliver on any one day at least 95% of the quantity of gas

requested to be delivered by Pipeline at Point(s) of Delivery which Pipeline is

obligated to deliver on a firm basis at such Point(s) of Delivery on such day up

to the MDWQ, the Reservation Charge shall be decreased by the amount of the

Reservation Charge Adjustment (as set forth on Sheet No. 43 of Pipeline's FERC

Gas Tariff, Volume No. 1, as such sheet may be revised, superseded or

supplemented from time to time) multiplied by the quantity of gas not delivered

up to the lesser of the total quantity of gas requested and not delivered, or the

MDWQ. Such Reservation Charge Adjustment shall be discounted in the case of an

executed service agreement containing a discounted Reservation Charge Rate in the

same proportion such Reservation Charge Rate is discounted from the maximum

Reservation Charge Rate.

 

3.5 Pipeline shall not be obligated to adjust the Reservation Charge

pursuant to Section 3.4 when Pipeline's failure to deliver on any one day at

least 95% of the quantity of gas requested by Customer to be delivered at

Point(s) of Delivery which gas Pipeline is obligated to deliver on a firm basis

at such Point(s) of Delivery on such day up to the MDWQ: