Texas Eastern Transmission Corporation
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/1993, Docket: RS92- 11-009, Status: Effective
Original Sheet No. 263 Original Sheet No. 263 : Effective
RATE SCHEDULE TABS-2
TRANSPORTATION AGGREGATION BALANCING SERVICE
1. AVAILABILITY
This Open-access Rate Schedule is available to any party (hereinafter
called the TABS-2 Party) which has requested transportation aggregation
balancing service pursuant to Section 3 of Texas Eastern Transmission
Corporation's (hereinafter called Pipeline) General Terms and Conditions
and, after review and acceptance of such request by Pipeline, has entered
into a service agreement with Pipeline for service under Rate Schedule
TABS-2. Such service agreement shall be in the form contained in
Pipeline's FERC Gas Tariff of which this Rate Schedule TABS-2 is a part.
2. APPLICABILITY AND CHARACTER OF SERVICE
This Rate Schedule TABS-2 shall permit a TABS-2 Party to pre-inject
gas and/or alter receipts into Pipeline's system for the purpose of
assisting Pipeline in attempting to avoid operational emergencies and/or
the necessity for issuing operational flow orders, as more fully set forth
in Section 3 herein, or, with Pipeline's consent, for the purpose of pre-
injecting gas into Pipeline's system in anticipation by TABS-2 Parties of
increased gas demand requirements as more fully set forth in Section 4
herein, or when necessary to alleviate gas supply shortages, as set forth
in Section 5 herein. The pre-injection of gas can be accomplished by
either (1) Pipeline's receipt of gas physically injected into its system at
Point(s) of Receipt or (2) Pipeline's retention, by displacement, of gas
otherwise scheduled for delivery out of its system at Point(s) of Delivery.
Gas retained by displacement shall be deemed delivered under the applicable
rate schedule and the applicable charges shall be paid by Customer to
Pipeline.
3. PIPELINE OPERATIONAL REQUIREMENTS
3.1 In the event Pipeline is willing to allow pre-injection of gas
into its system by TABS-2 Parties for the reasons set forth in Section 2 of
this Rate Schedule TABS-2, Pipeline shall post on the LINKþ System: (a) the
quantity of gas requested; (b) the TABS Service Point(s) at which such
quantity of gas is required; (c) the period of time during which conforming
offers will be accepted from TABS-2 Parties; and (d) whether TABS-2 Parties
must leave pre-injected gas in Pipeline's system until further notice from
Pipeline. Any pre-qualified TABS-2 Party may inform Pipeline during the
time period specified in the posting of its desire to inject gas into
Pipeline's system. Pipeline shall accept gas from TABS-2 Parties offered
in conformance with the request posted by Pipeline on a first-come, first
served basis.