Texas Eastern Transmission Corporation
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 12/01/2000, Docket: RP01- 69-000, Status: Effective
First Revised Sheet No. 253F First Revised Sheet No. 253F : Effective
Superseding: Third Sub Original Sheet No. 253F
RATE SCHEDULE VKFT
(Continued)
3. RATE
3.1 The applicable rates for service hereunder are set forth in the currently effective
Sheet No. 42B of this FERC Gas Tariff and are hereby incorporated herein. The rates in
this rate schedule are subject to adjustment pursuant to Sections 15.1, 15.3 and 15.6
of Pipeline's General Terms and Conditions and to the extent such service quantities
are not delivered hereunder for further transportation on Pipeline's system under one
or more of Pipeline's other rate schedules, Sections 15.2, 15.4 and 15.5 of Pipelines'
General Terms and Conditions. Unless Pipeline and Customer agree in writing upon a rate
for service provided hereunder, the rate applicable to a Customer for service hereunder
shall be the applicable maximum rate(s) as set forth on the effective Sheet No. 42B.
In the event a rate less than the applicable maximum rate(s) and not less than the
applicable minimum rate(s) is agreed upon, such rate shall be applicable for the period
agreed upon by Customer and Pipeline.
3.2 Customer shall pay Pipeline each month the sum of the following amounts:
(A) Reservation Charge:
The Reservation Charge Rate, as determined pursuant to Section 3.1 herein,
multiplied by the MDQ and multiplied by the number of days in the month; and
(B) Monthly Usage Charge consisting of the sum of the following daily charges:
(1) The Usage-2 Charge Rate, as set forth on Sheet No. 42B, multiplied by that
portion of the total quantity of gas deliveries on any day pursuant to the
executed service agreement, which is in excess of 110% of scheduled
service levels for such day.
3.3 Except as provided in Section 3.4 of this Rate Schedule, in the event Pipeline fails to
deliver on any one day at least 95% of the quantity of gas requested to be delivered by
Pipeline at Point(s) of Delivery which Pipeline is obligated to deliver on a firm basis
at such Point(s) of Delivery on such day up to the MDQ, the Reservation Charge shall be
decreased by the amount of the Reservation Charge Adjustment (as set forth on Sheet No.
42B of Pipeline's FERC Gas Tariff, Volume No. 1, as such sheet may be revised, superseded
or supplemented from time to time) multiplied by the quantity of gas not delivered up to
the lesser of the total quantity of gas requested and not delivered, or the MDQ and
multiplied by the number of days in the month. Such Reservation Charge Adjustment shall
be discounted in the case of an executed service agreement containing a discounted
Reservation Charge Rate in the same proportion such Reservation Charge Rate is discounted
from the maximum Reservation Charge Rate.