Texas Eastern Transmission Corporation

Sixth Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/01/1993, Docket: RP94- 20-000, Status: Effective

First Revised Sheet No. 247 First Revised Sheet No. 247 : Effective

Superseding: Original Sheet No. 247

RATE SCHEDULE IT-1

(Continued)

 

11. RATE SCHEDULES TS-2, SS-2, SS-3 AND ORIGINAL VOLUME NO. 2

CONVERSIONS

 

11.1 Those Rate Schedule TS-2 agreements previously entered into by

Customers with Pipeline for interruptible transportation service may be

converted at any time to Rate Schedule IT-1 Service Agreements, at the

Customers request, if Pipeline receives such request to convert by November

1, 1993. As of the effective date of such conversion, the rights and

obligations of the parties to the Rate Schedule TS-2 agreements shall be

determined pursuant to this Rate Schedule IT-1. Priority shall be based on

the date service originally commenced under Rate Schedule TS-2.

 

11.2 Customers under former Rate Schedules SS-2 and SS-3 may enter

into IT-1 Service Agreements for any level of interruptible transportation

service formerly provided under Rate Schedules SS-2 and SS-3, as of May 31,

1993. Priority shall be based on the date service originally commenced

under Rate Schedules SS-2 and SS-3 which was November 18, 1979 and March

20, 1984, respectively.

 

11.3 Those Original Volume No. 2 agreements previously entered into by

Customers with Pipeline for interruptible service under Rate Schedules X-

92, X-93, X-96, X-97 and X-116 may be converted at any time to Rate

Schedule IT-1 Service Agreements, at the Customer's request, if Pipeline

receives such request to convert by November 1, 1993. As of the effective

date of such conversion, the rights and obligations of the parties to the

Original Volume No. 2 agreements shall be determined pursuant to this Rate

Schedule IT-1. Priority shall be based on the date service originally

commenced under such Original Volume No. 2 agreement.

 

12. GENERAL TERMS AND CONDITIONS

 

All of the General Terms and Conditions of Pipeline's FERC Gas Tariff

of which this Rate Schedule is a part are applicable to this Rate Schedule

and are made a part hereof to the extent that such terms and conditions are

not contradicted by any provision herein.