Texas Eastern Transmission Corporation
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/1993, Docket: RS92- 11-009, Status: Effective
Original Sheet No. 245 Original Sheet No. 245 : Effective
RATE SCHEDULE IT-1
(Continued)
3. RATE
3.1 The applicable rates for service hereunder in each zone are set forth
in the currently effective Sheet No. 42 of this FERC Gas Tariff and hereby
incorporated herein. The rates in this Rate Schedule are subject to adjustment
pursuant to Section 15 of Pipeline's General Terms and Conditions. Unless
Pipeline and Customer agree in writing upon a rate for service provided
hereunder, the rate applicable to a Customer for service hereunder shall be the
applicable maximum rate(s) as set forth on the effective Sheet No. 42. In the
event a rate less than the applicable maximum rate(s) and not less than the
applicable minimum rate(s) is agreed upon, such rate shall be applicable for the
period agreed upon by Customer and Pipeline.
3.2 For Customers executing a service agreement for transportation which is
not solely a backhaul transportation arrangement, Customer shall pay Pipeline
each month a Monthly Usage Charge consisting of the sum of the following daily
charges:
(A) The Usage-1 Charge Rate, as determined pursuant to Section 3.1
herein, multiplied by that portion of the total quantity of gas
deliveries on any day pursuant to the executed service agreement,
which is not in excess of 110% of scheduled service levels for
such day.
(B) The Usage-2 Charge Rate, as set forth on Sheet No. 42, multiplied
by that portion of the total quantity of gas deliveries on any day
pursuant to the executed service agreement, which is in excess of
110% of scheduled service levels for such day.
3.3 For Customers executing a service agreement for transportation which is
solely a backhaul transportation arrangement, Customer shall pay Pipeline each
month a Monthly Usage Charge consisting of the sum of the following daily
charges:
(A) The Usage-1 Charge Rate, as determined pursuant to Section 3.1
herein, multiplied by that portion of the total quantity of gas
deliveries on any day pursuant to the executed service agreement,
which is not in excess of 110% of scheduled service levels for
such day.
(B) The Usage-2 Charge Rate, as set forth on Sheet No. 42, multiplied
by that portion of the total quantity of gas deliveries on any day
pursuant to the executed service agreement, which is in excess of
110% of scheduled service levels for such day.