Texas Eastern Transmission Corporation

Sixth Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 06/01/1993, Docket: RS92- 11-009, Status: Effective

Original Sheet No. 238 Original Sheet No. 238 : Effective

 

RATE SCHEDULE PTI

(Continued)

 

Customer's MDQ, which MDQ shall be determined by dividing Customer's scheduled

quantities of gas by 184; provided, however, to the extent transportation

hereunder is for purposes of injection into Pipeline's storage, the MDQ hereunder

shall not exceed the sum of (i) the Maximum Daily Injection Quantity (MDIQ)

and/or MDQ as specified in the applicable storage service agreement(s) with

Pipeline for whom gas is to be injected under such service agreement and (ii) to

the extent transportation hereunder is for purposes of injection into third party

storage, the quantity of gas such third party is willing to accept on a daily

basis for such Customer.

 

6. DETERMINATION OF DELIVERIES

 

If Pipeline delivers natural gas to Customer under this Rate Schedule at the

same Point(s) of Delivery on the same day that Pipeline delivers natural gas to

Customer under any other rate schedule, then the quantity of natural gas

delivered under this Rate Schedule shall be determined in accordance with the

provisions of Section 18 of Pipeline's General Terms and Conditions of this FERC

Gas Tariff.

 

7. IMPAIRMENT OF RECEIPTS AND DELIVERIES

 

Where Pipeline, on any day is unable to receive and/or deliver the total

requests of all of its Customers on Pipeline's system, then Pipeline shall limit

receipts and/or deliveries of gas hereunder in accordance with Section 4 of

Pipeline's General Terms and Conditions.

 

8. IMBALANCES

 

Except to the extent Point of Receipt and Point of Delivery imbalances are

reconciled and resolved pursuant to Rate Schedule(s) TABS-1 and/or MBA, as

applicable, imbalances shall be reconciled and resolved pursuant to Section 8 of

Pipeline's General Terms and Conditions.

 

9. GOVERNMENTAL AUTHORIZATIONS

 

Transportation service under executed PTI Service Agreements shall be

implemented pursuant to any applicable self-implementing authorizations or

program of the FERC for which Pipeline has filed or in which Pipeline has agreed

to participate.

 

10. GENERAL TERMS AND CONDITIONS

 

All of the General Terms and Conditions of Pipeline's FERC Gas Tariff of

which this Rate Schedule is a part are applicable to this Rate Schedule and are

made a part hereof to the extent that such terms and conditions are not

contradicted by any provision herein.