Texas Eastern Transmission Corporation
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/1993, Docket: RS92- 11-009, Status: Effective
Original Sheet No. 203 Original Sheet No. 203 : Effective
RATE SCHEDULE CDS
(Continued)
Usage Charge Rates will be assessed upon the zones of initial receipt and
ultimate delivery of each Dth on Pipeline's system.
3.3 For Customers executing a service agreement for transportation which is
solely a backhaul transportation arrangement, Customer shall pay Pipeline each
month the sum of the following amounts:
(A) Reservation Charge:
The Reservation Charge Rate, as determined pursuant to Section 3.1
herein, multiplied by the Applicable Billing Determinants; and
(B) Monthly Usage Charge consisting of the sum of the following daily
charges:
(1) The Usage-1 Charge Rate, as determined pursuant to Section
3.1 herein, multiplied by that portion of the total quantity
of gas deliveries on any day pursuant to the executed service
agreement, which is not in excess of 110% of scheduled
service levels for such day.
(2) The Usage-2 Charge Rate, as set forth on Sheet No. 26,
multiplied by that portion of the total quantity of gas
deliveries on any day pursuant to the executed service
agreement, which is in excess of 110% of scheduled service
levels for such day and less than 110% of Customer's maximum
daily contractual entitlement for such day.
(3) The Usage-3 Charge Rate, as set forth on Sheet No. 26,
multiplied by that portion of the total quantity of gas
deliveries on any day pursuant to the executed service
agreement, which is in excess of 110% of Customer's maximum
daily contractual entitlement for such day.
Usage Charge Rates will be assessed upon the zones of initial receipt and
ultimate delivery of each Dth on Pipeline's system.
3.4 In addition to all other charges hereunder, Customers shall pay
Pipeline the applicable Incremental Facility Charge, as set forth on Sheet No.
29, per month per Dth of additional MDQ for which each Customer contracted under
Pipeline's various incremental facility expansions. The additional Dth
applicable for each Customer under each applicable incremental facility expansion
are set forth on Sheet No. 29.
3.5 Except as provided in Section 3.6 of this Rate Schedule, in the event
Pipeline fails to deliver on any one day at least 95% of the quantity of gas
requested to be delivered by Pipeline at Point(s) of Delivery which Pipeline is
obligated to deliver on a firm basis at such Point(s) of Delivery on such day up
to the MDQ, the Reservation Charge shall be