Section 17, Pipeline is authorized to collect only a

single penalty equal to the highest applicable penalty.

 

17.2 A Customer's failure to comply with an Operational Flow Order

issued pursuant to Paragraph 5.9 and/or Section 14 herein

shall subject such Customer to a penalty in the amount of ten

dollars ($10.00) per MMBtu based upon Customer's variance from

the Operational Flow Order.

 

17.3 A Customer's failure to comply with Pipeline's curtailment

plan as set forth in Section 6 herein shall subject such

Customer to a penalty in the amount of ten dollars ($10.00)

per MMBtu based upon Customer's variance from Pipeline's

curtailment plan.

 

17.4 A Customer's failure to conform receipts and deliveries within

the forty-eight (48) hour period provided by Pipeline's notice

pursuant to Paragraph 5.6(b) herein or to correct actions

causing an imbalance which exceeds the greater of five percent

(5%) of scheduled quantities or 50 MMBtu within the forty-

eight (48) hour period provided by Pipeline's notice pursuant

to Paragraph 14.3 herein shall subject such Customer to a

penalty in an amount equal to the maximum rate for service

provided pursuant to Rate Schedule ITS, as set forth on

Tariff Sheet No. 4A, per MMBtu based upon the variance between

scheduled and allocated quantities at each point of interconnect.

 

17.5 To the extent that quantities of gas delivered from Pipeline's

system pursuant to Rate Schedule NNS exceed Customer's NNS

MDQ, Customer shall pay Pipeline ten dollars ($10.00) per

MMBtu for deliveries in excess of Customer's NNS MDQ.

 

17.6 A Customer whose actions result in the need for Pipeline to

divert gas from another Customer pursuant to Paragraph 5.5

herein shall be subject to a penalty in an amount equal to the

maximum rate for service provided pursuant to Rate Schedule

ITS, as set forth on Tariff Sheet No. 4A, per MMBtu based upon

the quantity of gas diverted.

 

17.7 A Customer's failure to comply with a notice issued by

Pipeline pursuant to Section 5.2 herein, instructing Customer

to restrict receipts or deliveries of gas to enable Pipeline

to maintain physical and operational control of its system,

shall subject such Customer to a penalty in an amount equal to