Mid Louisiana Gas Company
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/10/1999, Docket: RP99-280-002, Status: Effective
Second Revised Sheet No. 155A Second Revised Sheet No. 155A : Effective
Superseding: First Revised Sheet No. 155A
(C) The Intraday 1 Nomination Cycle: 10:00 am for
nominations leaving control of the nominating party;
10:15 am for receipt of nominations by the
transporter; 10:30 am to send Quick Response; 1:00 pm
for receipt of completed confirmations by transporter
from upstream and downstream connected parties; 2:00
pm for Transportation Service Provider to provide
scheduled quantities to affected shippers and point
operators, and to provide scheduled quantities to
bumped parties (notice to bumped parties); (central
clock time on the gas day). Scheduled quantities
resulting from Intraday 1 Nominations should be
effective at 5:00 pm on gas day.
(D) The Intraday 2 Nomination Cycle: 5:00 pm for
nominations leaving control of the nominating party;
5:15 pm for receipt of nominations by the transporter;
5:30 pm to Send Quick Response; 8:00 pm for receipt
of completed confirmations by transporter from
upstream and downstream connected parties; 9:00 pm
for Transportation Service Provider to provide
scheduled quantities to affected shippers and point
operators (central clock time on the gas day).
Scheduled quantities resulting from Intraday 2
Nominations should be effective at 9:00 pm on gas day.
Bumping is not allowed during the Intraday 2
Nomination Cycle.
(E) For purposes of GISB Standards 1.3.2 (ii), (iii), and
(iv), which is incorporated herein as Paragraph
15.1(i)(B), (C) and (D), "provide" shall mean for
transmittals pursuant to GISB Standards 1.4.x, receipt
at the designated site, and for purposes of other
forms of transmittal, it shall mean send or post.
(F) GISB Standard 1.3.2 (vi) is incorporated herein by
reference.