Mid Louisiana Gas Company
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/10/1999, Docket: RP99-280-002, Status: Effective
Fourth Revised Sheet No. 143 Fourth Revised Sheet No. 143 : Effective
Superseding: Third Revised Sheet No. 143
Pipeline determines in its reasonable judgment
that operating conditions will permit such
change, a late nomination may be implemented by
Pipeline subject to confirmation.
(3) Customers shall have the right, on or after the
first day of flow under any scheduled
nomination, to submit a new nomination
for any day complying with the procedures
set forth in Paragraph 15.1 (a) (1) and
15.1 (a) (2) of this section. Such new nomination
shall be implemented by Pipeline
in accordance with the timeline(s) set forth
in Paragraph 15.1.(i) and Paragraph 15.3 of
Pipeline's General Terms and Conditions and only
if such nomination is permitted, in Pipeline's
reasonable judgment, by Pipeline's system
operating conditions, and if such nomination may
be implemented, in Pipeline's reasonable
judgment, without detriment to any other
firm Customer. Such new nomination shall
specify Customer's anticipated service
requirements and the date(s) throughout which
such service is desired in addition to any other
data elements as required by Paragraph 15.1(a)(1)
hereof.
(4) In addition to the rights set forth hereinabove,
Pipeline shall allow, Customer to submit intra-
day nominations in accordance with the
timeline(s) set forth in Paragraph 15.1.(i)
hereof. Such intra-day
nomination can be used to request increases or
decreases in total flow, changes to receipt
points, or changes to delivery points of
scheduled gas. Such revised nominations shall
designate the contract under which such service
is requested, the date and time for which such
service is to become effective, the requested
daily flow rates at each receipt point, and all
other data elements as required.