Mid Louisiana Gas Company

Third Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 09/01/1996, Docket: RP96-291-001, Status: Effective

Substitute First Revised Sheet No. 117 Substitute First Revised Sheet No. 117 : Effective

Superseding: ORIGINAL SHEET NO. 117

 

6.4 (a) Should a Customer desire waiver of the capacity

curtailment provisions of Paragraph 6.3(a) during

emergency situations in order to prevent injury to life

or property or to provide minimum plant protection,

Pipeline shall retain the right but not the obligation

or duty to provide for an exception in all or part to

its curtailment provisions set forth herein.

 

(b) The Customer seeking waiver shall inform Pipeline and

Pipeline shall inform all affected Customers as to the

extent of the situation or emergency giving rise to the

necessity for an exception to the curtailment provisions

of this Section 6 and the measures that have been taken

to reduce the extent of the situation or emergency.

 

(c) A Customer whose gas was diverted under this Paragraph

6.4 shall have the option to be compensated for such gas

by the Customer whose request for emergency relief

resulted in a loss of transportation capacity or the

need for Pipeline to divert gas either through the

delivery of quantities of gas equal to the quantities of