Enbridge Pipelines (Midla) Inc.

Second Revised Volume No. 2

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 10/01/2001, Docket: GT01- 30-000, Status: Effective

Original Sheet No. 75 Original Sheet No. 75 : Effective

 

 

 

 

RATE SCHEDULE X-8

(Continued)

 

ARTICLE IV

 

TRANSPORTATION FOR SOUTHERN

 

Enbridge Pipelines (Midla), Inc. (formerly known as Mid Louisiana)

will accept for Southern's account at the delivery point specified in the gas

purchase contract between Mobil and Enbridge Pipelines (Midla), Inc. (formerly

known as Mid Louisiana) dated April 11, 1975), that part of the gas produced

in Block 140, which Southern purchases from Mobil, its successors, or assigns,

pursuant to the assignment by Enbridge Pipelines (Midla), Inc. (formerly known

as Mid Louisiana) to Southern dated April 18, 1975. Enbridge Pipelines

(Midla), Inc. (formerly known as Mid Louisiana) will redeliver such volumes to

Southern at the Grand Bay Exchange Point at no cost to Southern.

 

 

ARTICLE V

 

FACILITIES

 

1. Enbridge Pipelines (Midla), Inc. (formerly known as Mid Louisiana)

shall install, pay for, maintain and operate, or cause to be installed,

maintained and operated: (i) a connecting pipeline, of not less than six

inches in diameter, for the transmission of its and Southern's gas from the

point where Mobil makes the Block 140 gas available in Plaquemines Parish,

Louisiana to the Grand Bay Exchange Point; and (ii) a meter and appurtenant

facilities at the point in Plaquemines Parish where Mobil makes the Block 140

gas available. Enbridge Pipelines (Midla), Inc. (formerly known as Mid

Louisiana) shall be responsible for measurement at this point.

 

2. Southern shall install, pay for, maintain and operate a tap on its

line at the Grand Bay Exchange Point.

 

3. Enbridge Pipelines (Midla), Inc. (formerly known as Mid Louisiana)

shall install, pay for, maintain and operate: (i) a connection between the

outlet of Ashland's Cargas Compressor Station and its existing lines adjacent

thereto; (ii) taps on its lines; and (iii) a meter and appurtenant facilities

at the outlet of the station. Enbridge Pipelines (Midla), Inc. (formerly known

as Mid Louisiana) shall be responsible for measurement at the Cargas Exchange

Point.

 

4. Southern and Enbridge Pipelines (Midla), Inc. (formerly known as Mid

Louisiana) shall install and Enbridge Pipelines (Midla), Inc. (formerly known

as Mid Louisiana) shall operate the facilities necessary for the