Enbridge Pipelines (Midla) Inc.
Fourth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/2001, Docket: GT01- 30-000, Status: Effective
Original Sheet No. 147 Original Sheet No. 147 : Effective
9.8 If presentation of a bill by Pipeline is delayed after the 9th
business day of the month, then the time of payment shall be
extended accordingly unless Customer is responsible for such
delay.
10. CONSTRUCTION OF NEW FACILITIES AND ASSOCIATED FEES
10.1 Pipeline shall have no obligation to construct facilities to
receive, redeliver, transport, or exchange natural gas; provided,
however, if Customer requests and Pipeline, on a non-
discriminatory basis, elects to construct such facilities,
Customer shall, at Pipeline's request, reimburse Pipeline for all
costs incurred for facilities Pipeline constructs to receive,
redeliver, transport or exchange, gas volumes for Customer.
10.2 Customer shall reimburse Pipeline for any filing or other fees
which Pipeline is obligated to pay to the FERC or any other
governmental authorities to implement or continue any service
provided pursuant to this FERC Gas Tariff. Any reimbursement due
Pipeline by Customer pursuant to this Section 10 shall be due and
payable to Pipeline within ten (10) days of receipt by Customer of
Pipeline's invoice for such reimbursement.
10.3 In the event Pipeline elects to construct facilities pursuant to
this Section 10, any gas which is lost as a result of such
construction shall be replaced by Customer at a time and place and
in such quantities as determined by Pipeline; provided, however,
Customer shall not be responsible for replacing those quantities
lost due to the negligence of Pipeline.
11. LATERAL LINE POLICY
11.1 To the extent that Pipeline elects to provide service pursuant to
this FERC Gas Tariff, it shall be Pipeline's policy to finance,
construct, own, and operate laterals serving Customers. This
policy shall be applicable to the financing, construction,
ownership, and operation of laterals serving both existing and
prospective Customers under Pipeline's Rate Schedules contained in
this FERC Gas Tariff.