Enbridge Pipelines (Midla) Inc.
Fourth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/2001, Docket: GT01- 30-000, Status: Effective
Original Sheet No. 49 Original Sheet No. 49 : Effective
(c) The date on which Customer is notified that any facilities
necessary to provide the requested service are ready for
service; or
(d) The date on which any necessary governmental approvals or
authorizations are received and accepted by the appropriate
party.
3.4 Customer's Service Agreement shall be terminated if, after
commencement of initial service, Customer fails to nominate or
tender gas within thirty (30) days after notice by Pipeline of its
intent to terminate Customer's Service Agreement by reason of
failure of Customer to transport gas for a six (6) month
consecutive period.
3.5 Customer's failure to schedule transportation shall be excused by
an event of force majeure, as defined in Section 13 of the General
Terms and Conditions; provided, however, such failure to schedule
transportation shall be excused only for the duration of the force
majeure event.
4. RATE
4.1 The rate for interruptible transportation service provided under
this Rate Schedule shall be the amount negotiated by Pipeline and
Customer, which shall not be more than the maximum, nor less than
the minimum for this Rate Schedule as set forth on currently
effective Tariff Sheet No. 4A.
4.2 Pipeline shall have the right to retain one and one-half percent
(1.5%) of the quantities of gas delivered to Pipeline for Fuel
Reimbursement. Any change in such fuel rate shall be made
effective only at the beginning of a month.
4.3 Customer shall pay Pipeline the Annual Charge Adjustment ("ACA"),
as set forth on currently effective Tariff Sheet No. 4A.
4.4 Customer shall also pay Pipeline the applicable rates, charges,
and fees as set forth on currently effective Tariff Sheet No. 4A
or as may be assessed, required or permitted to