K N Wattenberg Transmission LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/01/1993, Docket: CP92-203-002, Status: Effective
Original Sheet No. 48 Original Sheet No. 48 : Effective
General Terms and Conditions - continued
meter. However, in the event Transporter does not
install a recording thermometer or temperature
compensated meter, Shipper may install a recording
thermometer and in such case the temperature so
recorded shall be used in correcting to a temperature
of sixty (60) degrees Fahrenheit.
(4) When orifice meters are used, the specific gravity of
the gas delivered hereunder shall be determined by
approved methods once a month, or as frequently as
necessary for reasonably accurate determination, and
the specific gravity so obtained shall be used in
computing volumes of gas delivered hereunder.
d. The components for determining the deviation from Boyle's
Law, at the pressure and temperature under which
delivered, shall be determined by tests at intervals of
twelve (12) months or at such shorter interval as is found
necessary. The correction factor determined by using
American Gas Association "Report Number Eight" or American
Gas Association "Project NX-19" shall be used in the
computation of deliveries until the next test.
e. The heating value of the gas delivered shall be determined
by approved recording calorimeters, gas samples or
chromatographs installed by Transporter at points on
Transporter's system in specified areas.
5. MEASURING EQUIPMENT.
a. Transporter agrees to install, operate and maintain on its
pipeline at or near each point of connection of the
facilities of Transporter and Shipper (or another party
which is transporting the gas on behalf of Shipper), a
meter or meters of standard type and design to measure all
of the gas to be delivered hereunder. Transporter also
agrees to install, operate and maintain at or near each
Point of Delivery such pressure regulating equipment as
may be necessary.