K N Wattenberg Transmission LLC

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 01/01/1999, Docket: RP99-104-000, Status: Effective

First Revised Sheet No. 66 First Revised Sheet No. 66 : Effective

Superseding: Original Sheet No. 66

 

General Terms and Conditions - continued

 

VOLUNTARY CONTRIBUTIONS MECHANISM

 

Pursuant to the GRI Settlement approved by FERC order issued

April 29, 1998, at Docket Nos. RP97-149-003, et al.,

[(83 FERC Para. 61,093 (1998))], Transporter and other pipelines

have agreed to be voluntary collection agents for Shippers who

voluntarily choose to contribute to GRI programs through a

“check-the-box” approach on pipelines’ invoices. The amounts

collected pursuant to the “check-the-box” mechanism will not be

part of Transporter’s jurisdictional rates and the FERC will not

review or approve any such amounts. The amounts contributed

by Shippers through the “check-the-box” mechanism

will be in addition to the amounts (if any) Transporter may

be required to collect as a GRI member by applying the GRI

Adjustment approved by FERC against the transactions specified

Subsection 21 (a) hereof. Through this “check-the-box”

mechanism, Shippers: (1) shall indicate the amounts they are

voluntarily contributing to GRI and (2) may indicate the

specific project(s) or project area(s) to which the amounts

are applicable.

 

e. REMITTANCE TO GRI

 

Transporter shall remit to GRI, not later than

fifteen (15) days after the receipt thereof, all

monies received by virtue of the GRI Adjustment

Charge and the “check-the-box” mechanism, less any amounts

properly payable to a Federal, State or Local authority

relating to the monies received hereunder. In addition, for

the amounts received through the “check-the-box” mechanism,

Transporter shall indicate to the GRI the amounts applicable

To specific project(s) and project area(s), if so

Indicated by Shipper(s).

 

22. FEDERAL ENERGY REGULATORY COMMISSION ANNUAL CHARGE ADJUSTMENT:

 

a. PURPOSE

 

For the purpose of funding of the FERC costs incurred in

any fiscal year, this Article 23 establishes

an Annual Charge Adjustment to be applicable to

Transporter's Rate Schedules as set forth on Sheet

No. 6 of this FERC Gas Tariff. Transporter shall

not recover any annual charge adjustment in a NGA Section 4

rate case.