K N Wattenberg Transmission LLC

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 06/01/1999, Docket: RP99-288-000, Status: Effective

Second Revised Sheet No. 34 Second Revised Sheet No. 34 : Effective

Superseding: Substitute First Revised Sheet No. 34

 

Interruptible Transportation Service – continue

 

(d) The Intra-day 2 Nomination Cycle: 5:00 p.m. for nominations leaving

control of the nominating party; 5:15 p.m. for receipt of

nominations by Transporter; 5:30 p.m. to send Quick Response; 8:00

p.m. for receipt of completed confirmations by Transporter from

upstream and downstream connected parties; 9:00 p.m. for

Transporter to provide scheduled quantities to affected shippers and

point operators (central clock time on the gas Day). Scheduled

quantities resulting from Intra-day 2 Nominations should be

effective at 9:00 p.m. on the gas Day. Bumping is not allowed

during the Intra-day 2 Nomination Cycle.

 

(e) For purposes of Section 6.2 (b)(c) and (d), “provide” shall mean,

for transmittals pursuant to standards 1.4.x, receipt at the

designated site, and for purposes of other forms of transmittal,

it shall mean send or post.

 

(f) Shipper shall include in any nomination: 1) the daily quantity of

gas to be received by Transporter including Shipper's transportation

volumes, 2) overrun quantities, may be requested on a

separate transaction, 3) any daily volumes to satisfy past

imbalances, 4) receipt points (primary and/or secondary), 5) the

daily quantity to be delivered by Transporter at each specified

delivery point (primary and/or secondary) on the desired gas day,

6) provide contract numbers for both upstream and downstream

parties, if known, and related processing agreement numbers,

7) Shipper defined beginning and ending dates. The total receipt

nominations, less other deductions, must equal the equivalent

thermal quantity of delivery nominations.

 

(g) All nominations, including intra-day nominations, shall be based on

daily quantity, thus, an intra-day nominator need not submit an

hourly nomination. Intra-day nomination shall include an effective

date. The interconnected parties will agree on the hourly

flow of the intra-day nomination, if not otherwise addressed in the

Service Agreement or Transporter's Tariff. All

nominations, excluding intra-day nominations, have rollover

options. Specifically, Shippers have the ability to

nominate for several days, months or years, provided the

nomination begin and end dates are within the term of the

Shipper's Service Agreement. Intra-day nomination s do not

rollover nor do they replace the remainder of a standing

nomination. There is no need to re-nominate if an intra-

day nomination modifies an existing nomination. Intra-day

nominations cannot cause a Shipper to exceed its MDTQ.