Florida Gas Transmission Company

Third Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/01/1993, Docket: RS92- 16-003, Status: Effective

Original Sheet No. 143 Original Sheet No. 143 : Superseded

 

GENERAL TERMS AND CONDITIONS

(continued)

 

(c) Determination of End-Use Classification -- The requirements

for natural gas usage at each Delivery Point or Division, in

the case of multiple Division Shippers where applicable,

shall be classified in accordance with the end-use priorities

set forth in Section 17A.1(b). Such classification shall be

conducted as follows:

 

(1) The requirements for natural gas usage for a customer

shall be established as necessary to accommodate

existing firm capacity at the Delivery Point or

Division, as applicable, as well as the possible

addition of firm capacity at the Delivery Point as a

result of the capacity relinquishment program set forth

in Section 18.

 

(2) A Data Verification Committee (DVC) is hereby

established for the purposes of reviewing and

establishing the requirements for natural gas usage at

each Delivery Point and for the purpose of classifying

such requirements in accordance with the end-use

priorities of Section 17A.1(b). Membership on the Data

Verification Committee is available to any of

Transporter's customers under Rate Schedules FTS-1,

SFTS, PTS and NNTS, who express a desire to

participate, and all Delivery Point Operators;

provided, however, that no person shall have more than

one representative on the Data Verification Committee.

Transporter shall be entitled to one representative on

the Data Verification Committee, but such

representative shall not be entitled to vote on the

decisions of the Committee. The Federal Energy

Regulatory Commission may have one representative on

the Committee, but such member shall not be entitled to

vote on the decisions of the Committee. Transporter's

representative and the Federal Energy Regulatory

Commission representative, if any, shall serve as co-

chairpersons of the Committee. The Data Verification

Committee shall have the authority to classify

requirements of electric generation users of natural

gas among the priority classifications set forth herein

in accordance with the end-use(s) of the electricity

generated from such natural gas, subject to the

demonstration, to the satisfaction of the DVC, that

such uses are: (i) served by electricity generated from

gas use and (ii) that alternative fuels are not

available at the electric generation facilities at

issue.