Florida Gas Transmission Company
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/1993, Docket: RS92- 16-003, Status: Effective
Original Sheet No. 142 Original Sheet No. 142 : Superseded
GENERAL TERMS AND CONDITIONS
(continued)
Priority 3. Essential industrial requirements for process
or feedstock use when established under Section 402 of the
Natural Gas Policy Act of 1978.
Priority 4. Industrial uses of customers whose total
requirements are less than 300 MMBtu per day; other
industrial requirements for feedstock or process use;
commercial requirements of 50 MMBtu per day or more.
Priority 5. Non-boiler fuel industrial requirements not
specified in priorities P-1, P-2, P-3, P-4, P-6, P-7, P-8 or
P-9 of 300 MMBtu per day or more.
Priority 6. Industrial boiler fuel requirements of 300
MMBtu per day or more, but less than 1,500 MMBtu per day not
otherwise specified in priorities P-1, P-2, P-3, P-4, P-5,
P-7, P-8 and P-9.
Priority 7. Industrial boiler fuel requirements of 1,500
MMBtu per day or more, but less than 3,000 MMBtu per day not
otherwise specified in priorities P-1, P-2, P-3, P-4, P-5,
P-6, P-8 and P-9.
Priority 8. Industrial boiler fuel requirements of 3,000
MMBtu per day or more, but less than 10,000 MMBtu per day
not otherwise specified in priorities P-1, P-2, P-3, P-4,
P-5, P-6, P-7 and P-9.
Priority 9. Industrial boiler fuel requirements of 10,000
MMBtu per day or more not otherwise specified in priorities
P-1, P-2, P-3, P-4, P-5, P-6, P-7 and P-8.
Unless specified by the Natural Gas Policy Act of 1978, the
definition of terms for these priorities of service shall be
those prescribed by the Federal Energy Regulatory Commission
and set forth in 18 C.F.R. Section 2.78(c), with the
exception that the term "boiler fuel" shall be defined as
"natural gas used as a fuel for the generation of steam or
electricity, not including the utilization of internal
combustion engines or turbines."