5. MEASURING EQUIPMENT
a. Installation and Operation. The Transporter will install,
maintain and operate, at its own expense except as provided in
Section 21 hereof at or near each point of delivery, a meter or
meters and other necessary measuring equipment by which the volume
of gas delivered to the Shipper shall be measured.
b. Check Measuring Equipment. The Shipper may install, maintain and
operate such check measuring equipment as it shall desire,
provided that such equipment shall be so installed as not to
interfere with the operation of the Transporter's measuring
equipment at or near the point of delivery. Upon notice to
Shipper, Transporter shall have access to such check measuring
equipment at all reasonable hours, but the reading, calibrating
and adjusting thereof and the changing of charts shall be done
only by the Shipper.
c. Access to Equipment and Records. Both the Transporter and the
Shipper shall be notified and shall have the right to be present
at the time of any installing, reading, cleaning, changing,
repairing, inspecting, calibrating or adjusting done in connection
with the other's measuring equipment used in measuring deliveries
hereunder. Delivery Point Operator shall have the right to access
Transporter's remote flow calculation, and shall have the right to
install equipment at its own expense which enables such Delivery
Point Operator to access Transporter's remote flow calculation for
its own use, provided that the installation of said equipment does
not interfere with Transporter's equipment. The records from such
measuring equipment shall remain the property of the owner, who
upon request will submit to the other such records and charts,
together with calculations therefrom, for the other's inspection
and verification, subject to return within ten (10) days after
receipt thereof.
d. Care in Installation. All installations of measuring equipment,
applying to or affecting deliveries of gas, shall be made in such
manner as to permit an accurate determination of the volume of gas
delivered and ready verification of the accuracy of measurement.
Reasonable care shall be exercised by both the Transporter and the
Shipper in the installation, maintenance and operation of pressure
regulating equipment so as to avoid, so far as practicable, any
inaccuracy in the determination of the volume of gas delivered
hereunder.