Florida Gas Transmission Company
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/2001, Docket: RP01-509-000, Status: Effective
Forty-Fourth Revised Sheet No. 8B Forty-Fourth Revised Sheet No. 8B : Superseded
Superseding: Forty-Third Revised Sheet No. 8B
Rates - Cents per MMBtu
WESTERN DIVISION TRANSPORTATION
Maximum Rates
Including Surcharge
Rate Facility Service Facility Service
Schedule Section Description Charge Charge Charge 4/ Charge
Maximum Minimum Maximum Minimum
FTS-WD 4 FIRM TRANSPORTATION 3/
Forward Haul 8.01¢ 0.00¢ 1/ 0.37¢ 2/ 8.31¢ 1/+0.91¢
Backhaul/Exchange 8.01¢ 0.00¢ 1/ 0.00¢ 8.31¢ 1/+0.91¢
TCR Reservation Charge and 636 Reservation Charge
to Applicable Shippers pursuant to Section 24
of the General Terms and Conditions 0.00¢
GRI Demand Surcharge to Applicable High Load Factor
Shippers pursuant to Section 23 of the General
Terms and Conditions 0.30¢
GRI Demand Surcharge to Applicable Low Load Factor
Shippers pursuant to Section 23 of the General
Terms and Conditions 0.18¢
GRI Volumetric Surcharge to Applicable Shippers pursuant
to Section 23 of the General Terms and Conditions 0.70¢
ACA Surcharge to Applicable Shippers pursuant to
Section 22 of the General Terms and Conditions 0.21¢
TCR Usage Surcharge to Applicable Shippers pursuant
to Section 24 of the General Terms and Conditions 0.00¢
In addition to any fuel charges by Transporting Pipeline, the
Fuel Reimbursement Charge Percentage for deliveries under
Rate Schedules FTS-WD, FTS-1 and FTS-2 pursuant to Section 27
of the General Terms and Conditions is 0.50% per compressor
station up to a maximum of 2.40%
1/ Service Charge applicable to each MMBtu delivered shall be 0.28¢/MMBtu plus .07¢/MMBtu per 25 miles or
any portion thereof in excess of 100 miles.
2/ Quantities delivered from an upstream FTS-WD shipper confirmed as receipts by a downstream shipper under
a Western Division Rate Schedule FTS-WD shall not be assessed a Facility Charge, Service
Charge or other surcharges, but shall be assessed a charge equal to .07¢/MMBtu per 25 miles or
any portion thereof.
3/ 100% Load Factor Rate shall equal the sum of the Facility and Service Charge.
4/ Reflects High Load Factor GRI Demand Surcharge. The maximum Facility Charge for Low Load Factor Shippers
is 8.19¢ per MMBtu.