CNG Transmission Corporation
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 01/10/2000, Docket: RP00-135-000, Status: Effective
Original Sheet No. 397A Original Sheet No. 397A : Superseded
GENERAL TERMS AND CONDITIONS
Construction of Delivery Tap Facilities
37. Construction of Delivery Tap Facilities.
37.1 For the purposes of this Section 37, "Requested
Facilities" shall mean Taps, M&R Equipment and
Laterals. Requested Facilities shall not include
major expansion of transmission facilities. "Tap"
shall mean a delivery tap and shall include, but
shall not be limited to, flanges and block valves
and sufficient pipeline from the Pipeline's
existing transmission facilities to the edge of
Pipeline's right-of-way. "M&R Equipment" shall
include miscellaneous connecting pipeline to the
tap, meters, compression, flow and pressure
regulators, filters/separators, gas heaters,
flanges, check valves, electronic gas measurement,
communication equipment and gas conditioning and
odorization equipment other than equipment
included in the Tap. "Lateral" shall mean any
transmission pipeline extension (other than a
mainline extension) built by Pipeline from an
existing transmission pipeline facility or new Tap
to deliver gas to or on behalf of one or more
Customers, including new delivery points and
enlargements or replacements of existing laterals.
"Construction" shall mean the construction,
modification, rearrangement or installation by
Pipeline or its designee of Requested Facilities
to perform any service, including any Requested
Facilities necessary for Pipeline to deliver gas
to, or measure any gas delivered to or on behalf
of any Customer requesting Pipeline's construction
of such facilities.
37.2 A party shall submit a request for facilities
under Section 11.A.1. requesting Pipeline to
construct Requested Facilities in conjunction with
a request for transportation services ("Requesting
Customer"). Pipeline will receive and process all
such all such requests for construction of
Requested Facilities in a manner that is not
unduly discriminatory.
37.3 Pipeline shall construct Requested Facilities
under the conditions provided below:
A. Requested Facilities shall be located at points that,
in Pipeline's reasonable judgment, are the most practical,
convenient and readily accessible sites; provided, however,
Pipeline shall approve