CNG Transmission Corporation
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 01/05/1998, Docket: CP96-492-008, Status: Effective
First Revised Sheet No. 394 First Revised Sheet No. 394 : Superseded
GENERAL TERMS AND CONDITIONS
Conditions Applicable to Storage Services
35. CONDITIONS APPLICABLE TO STORAGE SERVICES
35.1 DETERMINATION OF DELIVERIES, INJECTIONS AND WITHDRAWALS
The quantities of gas injected into storage for Customer's
account and withdrawn from storage and delivered to
Customer on any Day shall be determined by Pipeline's
meters at or near the points of delivery when gas is
delivered to Customer or Pipeline under a storage service
Rate Schedule only. When gas is delivered to Customer or
Pipeline under a storage service Rate Schedule and other
rate schedule(s) on the same Day, then the gas delivered
under the storage service Rate Schedule shall be the
quantity scheduled for injection or withdrawal on such Day
by Customer and Pipeline, subject to any adjustments
required under Rate Schedule FTNN. Pipeline shall keep
accurate records of quantities injected and withdrawn for
Customer's account, and of Customer's Storage Gas Balance,
which records shall be made available to Customer at its
written request.
35.2 BILLING ADJUSTMENTS
A. Demand and Storage Capacity Charge Adjustments. If
during the Summer Period, Pipeline is unable to inject
into storage quantities of gas nominated during such
period by Customer for injection and tendered to Pipeline
at any Primary Receipt Point specified under a storage
Service Agreement, then the Storage Demand Charge and the
Storage Capacity Charge shall be reduced in the following
manner: If, at the end of the Summer Period, Customer's
Storage Gas Balance is less than Customer's Storage
Capacity due solely to Pipeline's inability to inject gas
in accordance with Section 7 of the applicable Rate
Schedule, then the Storage Demand Charge applicable for
the current Storage Year shall be that part of the total
Storage Demand Charge herein provided which Customer's
Storage Gas Balance as of such date bears to Customer's
Storage Capacity. The same proportionate reduction shall
be made in the Storage Capacity for the same one-year
period.
B. Demand Charge Adjustment. If Pipeline fails or is unable
to deliver during any one or more Day the quantity of
natural gas which Customer desires to take at a Primary
Delivery Point, up to the maximum quantity which Pipeline
is obligated by the Service Agreement to deliver to
Customer at such point, subject to the limitations of
Section 8 of the applicable Rate Schedule, then the
Storage Demand Charge payable hereunder for that month
shall be reduced by an amount equal to that percentage of
the Demand Charge Adjustment set forth at the currently