GENERAL TERMS AND CONDITIONS
Capacity Release
12. Whether the Releasing Customer will entertain
contingent bids, and if so, (a) the time period
during which each contingent bidder must clear
its contingency, and (b) whether, and for what
time period, the next-highest bidder will be
utilizing the subject capacity, or if no winning
bidder is currently utilizing the subject
capacity, then to the bidder who submitted its
winning bid first in time; provided that if a
Designated Replacement Customer submits a
"winning bid," then Pipeline must contract with
such Designated Replacement Customer.
13. Any other conditions applicable to the release.
a. If a release includes the aggregation of
capacity on other pipelines in addition to
Pipeline, the maximum rate to be charged for
such aggregated capacity (by all parties) to
Replacement Customer may not exceed the sum
of the maximum rates applicable to each
affected pipeline's service. Releasing
Customer is responsible for posting such
aggregate releases on the bulletin board of
each pipeline upon which capacity is
released.
b. With the consent of the affected Releasing
Customers, Pipeline may combine releases
posted by several Releasing Customers into
one replacement contract to improve
marketability.
G. Within the posted bid period, a bidder seeking
capacity at terms that meet or exceed the minimum
terms of the release must post its complete bid on
Pipeline's EBB.
1. Such bids must be in the most current form of Bid
Agreement, as posted on Pipeline's EBB, which
when executed by Pipeline will constitute a
binding contract.
2. The name of the bidder will not be revealed on
Pipeline's EBB unless the bidder submits a
winning bid.