CNG Transmission Corporation
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 01/05/1998, Docket: CP96-492-008, Status: Effective
Second Revised Sheet No. 130 Second Revised Sheet No. 130 : Superseded
Superseding: Original Sheet No. 130
FTNN RATE SCHEDULE
Firm Transportation, No-Notice Service
B. Pipeline will accommodate such request, provided
that such request is made: (1) during a non-peak
storage withdrawal period; (2) when an operational
flow order limiting storage withdrawals is not in
effect; (3) when storage inventories are at or above
levels that will enable Pipeline to provide such
service without limiting firm services to other
customers or imposing an operational flow order on
Pipeline's system; (4) when Customer's Storage Gas
Balance is equal to or greater than the excess gas
requested; and (5) Customer has provided prior
notice as required by Customer's Transporter, if
any, and Customer's Transporter has confirmed to
Pipeline that it will accept the tendered
quantities.
C. Pipeline will issue an operational flow order in
accordance with Section 11B of the General Terms and
Conditions of this Tariff when conditions preclude
use of the "From Customer's Balance" provisions on
either a system-wide basis or on any particular
segment of Pipeline's system.
D. For any storage quantities delivered hereunder in
excess of 102% of Customer's combined daily
withdrawal entitlement under Rate Schedules GSS
and GSS-II Pipeline will charge Customer the "From
Customer's Balance" rate. Customer's Storage Gas
Balance under one or more of these Rate Schedules
will be reduced by all quantities delivered
including those delivered in excess of Customer's
combined daily withdrawal entitlement.
E. If a Customer has lost its supply being delivered by
Tennessee Gas Pipeline Company ("Tennessee") to
Pipeline, and Customer requests replacement for such
supply under "From Customer's Balance" provisions,
then Pipeline, at its option, may provide such "From
Customer's Balance" quantities to Customer from the
southern part of Pipeline's system to Tennessee in
Tennessee's Zone 3, and transport such gas on
Tennessee for redelivery to Pipeline. This service
shall be provided for no more than 72 hours, with a
total quantity (for all Customers) of no more than
200,000 Dt per Day.