FTNN RATE SCHEDULE
Firm Transportation, No-Notice Service
H. All other applicable rates, charges, and penalties as
set forth in the General Terms and Conditions of
Pipeline's Tariff, including, but not limited to, any
applicable incremental rate and fuel provisions in
accordance with Section 11.A.1.J. of the General Terms
and conditions and as listed on Sheet No. 37.
5.2 Pipeline will retain the percentage(s) of receipts set
forth on Sheet Nos. 32, 33 and 37 (as applicable) as the
Transportation Service Fuel Retention Percentage and/or the
Gathering Service Fuel Retention Percentage; provided,
however, that Pipeline will not retain fuel in those
instances where the transaction does not cause Pipeline to
use fuel.
5.3 Pipeline may elect to offer to transport at a rate that is
below the maximum but no less than the minimum rates set
forth on Sheet Nos. 32, 33 and 37 (as applicable) to this
Rate Schedule. However, Pipeline is not obligated to offer
to transport gas at any rates less than the maximum rates.
5.4 Small Customers that comply with the conditions set forth
in Section 10, below, are eligible for a one-part rate that
shall be designated as the FTNN(SC) rate on Pipeline's
tariff sheets. The one-part rate shall be calculated to
substitute for the Reservation Charge and the Usage Charge,
identified in Section 5.1 above, but shall not excuse
Customer from payment of any of the other charges
identified in this Section 5 or the General Terms and
Conditions of this Tariff.
6. RECEIPTS AND DELIVERIES
6.1 Each executed Service Agreement shall specify Primary
Receipt and Primary Delivery Points.
A. Each executed Service Agreement shall specify the
maximum quantities that Pipeline is obligated to
receive on any Day at each Primary Receipt Point.
Pipeline shall also receive, at the Receipt Point(s),
a quantity for fuel retention. Under the executed
Service Agreement, the sum of the quantities specified
at each Primary Receipt Point shall not exceed the
MDTQ.
B. Each executed Service Agreement may state the maximum
quantities that Pipeline is obligated to deliver on
any Day at each Primary Delivery Point.