CNG Transmission Corporation

Second Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 01/01/1996, Docket: RP94- 96-015, Status: Effective

Substitute Third Revised Sheet No. 121 Substitute Third Revised Sheet No. 121 : Superseded

Superseding: Substitute Second Revised Sheet No. 121

FTNN RATE SCHEDULE

Firm Transportation, No-Notice Service

 

H. All other applicable rates, charges, and penalties as

set forth in the General Terms and Conditions of

Pipeline's Tariff, including, but not limited to, any

applicable incremental rate and fuel provisions in

accordance with Section 11.A.1.J. of the General Terms

and conditions and as listed on Sheet No. 37.

5.2 Pipeline will retain the percentage(s) of receipts set

forth on Sheet Nos. 32, 33 and 37 (as applicable) as the

Transportation Service Fuel Retention Percentage and/or the

Gathering Service Fuel Retention Percentage; provided,

however, that Pipeline will not retain fuel in those

instances where the transaction does not cause Pipeline to

use fuel.

5.3 Pipeline may elect to offer to transport at a rate that is

below the maximum but no less than the minimum rates set

forth on Sheet Nos. 32, 33 and 37 (as applicable) to this

Rate Schedule. However, Pipeline is not obligated to offer

to transport gas at any rates less than the maximum rates.

 

5.4 Small Customers that comply with the conditions set forth

in Section 10, below, are eligible for a one-part rate that

shall be designated as the FTNN(SC) rate on Pipeline's

tariff sheets. The one-part rate shall be calculated to

substitute for the Reservation Charge and the Usage Charge,

identified in Section 5.1 above, but shall not excuse

Customer from payment of any of the other charges

identified in this Section 5 or the General Terms and

Conditions of this Tariff.

 

6. RECEIPTS AND DELIVERIES

 

6.1 Each executed Service Agreement shall specify Primary

Receipt and Primary Delivery Points.

A. Each executed Service Agreement shall specify the

maximum quantities that Pipeline is obligated to

receive on any Day at each Primary Receipt Point.

Pipeline shall also receive, at the Receipt Point(s),

a quantity for fuel retention. Under the executed

Service Agreement, the sum of the quantities specified

at each Primary Receipt Point shall not exceed the

MDTQ.

B. Each executed Service Agreement may state the maximum

quantities that Pipeline is obligated to deliver on

any Day at each Primary Delivery Point.