FT RATE SCHEDULE

Firm Transportation Service

 

5.3 Pipeline may elect to offer to transport at a rate that is below

the maximum but no less than the minimum rates set forth on

Sheet Nos. 32, 33, and 37 as applicable to this Rate

Schedule. However, Pipeline is not obligated to offer to

transport gas at any rates less than the maximum rates.

 

5.4 Small Customers that comply with the conditions set forth

in Section 10, below, are eligible for a one-part rate that

shall be designated as the FT(SC) rate on Pipeline's tariff

sheets. The one-part rate shall be calculated to substitute

for the Reservation Charge and the Usage Charge, identified

in Section 5.1 above, but shall not excuse Customer from

payment of any of the other charges identified in this Section

5 or the General Terms and Conditions of this Tariff.

 

6. RECEIPTS AND DELIVERIES

 

6.1 Each executed Service Agreement shall specify Primary

Receipt and Primary Delivery Points.

 

A. Each executed Service Agreement shall specify the

maximum quantities that Pipeline is obligated to

receive on any Day at each Primary Receipt Point.

Pipeline shall also receive, at the Receipt

Point(s), a quantity for fuel retention. Under

the executed Service Agreement, the sum of

the quantities specified at each Primary Receipt

Point shall not exceed the MDTQ.

 

B. Each executed Service Agreement may state the

maximum quantities that Pipeline is obligated to

deliver on any Day at each Primary Delivery Point.

This quantity shall be Pipeline's Maximum Daily

Delivery Obligation ("MDDO") at each point.

 

1. If no MDDO is stated for a Primary Delivery

Point, then Pipeline's obligation to deliver

gas to Customer at such point shall be

limited to the quantities that Pipeline is

able to deliver at such point using facilities

in existence as of May 18, 1992,

without adversely